15
STRAIGHT WALL PANEL AND CONNECTOR ASSEMBLY
NOTE: Use of cooking spray is recommended on the first few
inches of the splines to ease assembly. DO NOT use petroleum
based lubricants (WD-40).
Ease of spline installation depends
on level and parallel wall joints.
Once bottom track is assembled, begin installing wall panels
Drawings are for illustrative purposes and are not to scale.
1. Place a straight panel connector 3” from the end of
a channel.
2. Stand a straight panel next to the connector in the channel.
Install a 52” spline to join the panel and connector on the
inside of the pool.
3. Slide short spline (5 3/4”) into the outside
of the pool wall and connector.
4. Slide extended “T” spline down on top
of the short spline.
5. Slide a 2nd short spline down on top
of the extended spline.
6. Place the 2nd oval straight panel
connector into the channel.
7. Place the 2nd panel into the channel
and install splines as in steps 2-6.
(52” splines on inside of pool; short and
extended “T” splines on the outside of pool).
Continue assembling down the channel until
an oval straight panel connector is 3” from
the other end of the channel.
8. Install first radius panel at each end of the
channel to add stability to the assembled
straight panels. The first radius panels will
overlap 3” into the channel. Using a 7/16” bit,
drill through the inner bottom channel and
wall panel, where the radius panel overlaps
the channel. Then install included 2 ½” bolt
and nut.
9. Install the straight panels on the other
side of the pool.
3” space
Short Splines - 5 3/4”
Extended “T” Splines
Standard 52” Splines
(OUTSIDE POOL)
(OUTSIDE POOL)
(INSIDE POOL)
Straight Wall
Connector
FIRST
PANEL
(outside pool)
SECOND
PANEL
(outside pool)
*
EXTENDED “T” SPLINES
STRAIGHT PANEL
CONNECTOR
STANDARD
52” SPLINE
STANDARD
52” SPLINE
STRAIGHT WALL PANEL
STRAIGHT WALL PANEL
*
3” channel
overlap
RADIUS
PANEL
(outside pool)