5.3
Starting
Control panel
Control panel
Procedure
To prevent that wet air gets into the compressed air circuit, it is advised to follow next procedure:
Step
Action
1
Switch on the main supply to the dryer a few minutes before starting, to allow the Infologic²
and the flow switch to initialize.
2
If installed, close the dryer bypass valve and the dryer outlet valve (customers installation).
3
Open the dryer air inlet valve (customers installation) and pressurize the dryer.
4
Press start button (10).
After a few seconds the dryer is started.
5
Approximately 5 minutes later, open the dryer air outlet valve (customers installation).
6
Approximately 10 minutes later, the dew point will be stabilized.