System dimensions

—Select a rack mounting solution that has the appropriate depth to accommodate 

the following: 

– All of the system components.
– All of the mounting kits and associated rails.
– Any additional rack-mounted PDUs. 

 

System weight

—Select a rack mounting solution that can withstand the following:

– The static loads required for a P100E3 system. 
– The dynamic loads required if a system will be moved from the installation location. 

.

Cable management

—The system is designed so the cables are wired at the back of the system. 

Ensure that the system cabling can be routed safely and efficiently through the selected route.

Grounding

—Ensure that both the electrical components used to power the system and the rack itself 

can be grounded safely.

2.4  Delivery route inspection

During the receiving process, the system will need to be moved through the facility until it reaches the data 

center or computer room where it will be installed. This section describes the considerations that the 

installation team should make before receiving the system and moving it through the facility.

2.4.1  Walking path inspection

Walking paths must be clear of obstructions and wide enough to allow passage of the packaged system 

(44.5in. x 51in.) to the location where it will be unpacked. The following is a list of obstructions to 

consider when conducting a walking path inspection:

Cables

—Consider removing cables, including ramped cable covers, from the walking path before 

moving the pallet. Leaving the cables in place creates a safety hazard for the installation team and can 

damage the cables.

Lift Locations

—There may be locations along the walking path where the system must be lifted in 

order to proceed. Make sure that lift equipment is available at this location on the day of the delivery.

Elevators

—Ensure that any elevators that will be required to lift the equipment to the data center/

computer room are rated to carry the full load of the system plus passengers.

Security

—Make sure that all site security requirements adhered to and that all personnel are made 

aware of the parameters under which they must work.

2.5  Build space requirements

The ActiveScale P100E3 is delivered on a pallet and installed on-site. This section describes the space 

required for unpacking and installation.

Table 2

-

1. Footprint of packaging

Packaging item

Footprint

P100E3 node packaging

Width—

35 in (881 mm)

Depth—

51 in (1295 mm)

Height—

9.2 in (234 mm) Verify this

Summary of Contents for ActiveScale P100E3

Page 1: ...ActiveScale 6 68926 04 Rev A with ActiveScale OS 6 1 0 software P100E3 Site Requirements Guide...

Page 2: ...gistered trademarks or trademarks of Quantum Corporation and its affiliates in the United States and or other countries All other trademarks are the property of their respective owners Quantum specifi...

Page 3: ...P100E3 site requirements 11 2 1 Warnings and cautions 11 2 2 Environmental requirements 11 2 2 1 Airflow requirements 11 2 3 Rack requirements 11 2 4 Delivery route inspection 12 2 4 1 Walking path i...

Page 4: ...ActiveScale P100E3 Site Requirements Guide 4...

Page 5: ...Guide List of tables 5 List of tables Table 1 1 System specification summary 10 Table 2 1 Footprint of packaging 12 Table 2 3 Space requirement specifications 13 Table 2 2 Footprint of components 13 T...

Page 6: ...ActiveScale P100E3 Site Requirements Guide List of tables 6...

Page 7: ...ActiveScale P100E3 Site Requirements Guide List of figures 7 List of figures Figure 1 1 ActiveScale P100E3 system layout 9 Figure 2 1 Minimum servicing space required 13...

Page 8: ...ActiveScale P100E3 Site Requirements Guide List of figures 8...

Page 9: ...tem needs to make before integrating the system at the site where the system will be deployed This document should be used by the systems architect system planner and site manager and teams which plan...

Page 10: ...irements typical maximum N A 3 node 1 85 to 2 03 kW Relative humidity 20 to 95 non condensing 20 to 80 non condensing Relative humidity gradient 30 per hour maximum 30 per hour maximum System width an...

Page 11: ...ge due to overheating 2 2 1 Airflow requirements Use the following guidelines to ensure proper system airflow The airflow in and out of the equipment must not be restricted Controlled air conditioners...

Page 12: ...path inspection Walking paths must be clear of obstructions and wide enough to allow passage of the packaged system 44 5in x 51in to the location where it will be unpacked The following is a list of o...

Page 13: ...Before moving the system verify that the rack can support the dynamic load of the system weight during movement 2 6 Servicing space requirements Important Mounting a PDU or other equipment vertically...

Page 14: ...cessive current spike created by all the components powering on simultaneously To prevent the potentially negative effects of excessive inrush current on the system Quantum Corporation recommends sele...

Page 15: ...iber These cables must comply with the Ethernet 10GBASE SR standard Ensure that you do not exceed the specified maximum 10GBASE SR cable length for the cable type chosen For example do not exceed a le...

Page 16: ...ActiveScale P100E3 Site Requirements Guide 16...

Page 17: ...ther assistance contact the Quantum Corporation Support Center Region Support Contact North America 1 800 284 5101 toll free 1 720 249 5700 EMEA 1 800 7826 8888 toll free 49 6131 324 185 Asia Pacific...

Reviews: