ActiveScale™ P100E3 Site Requirements Guide

11

2 ActiveScale P100E3 site requirements

This section describes the power, environmental, and space requirements for the ActiveScale P100E3.

Topics:

Warnings and cautions 

on page 11

Environmental requirements 

on page 11

Rack requirements 

on page 11

Delivery route inspection 

on page 12

Build space requirements 

on page 12

Servicing space requirements 

on page 13

PDU requirements 

on page 14

Network requirements 

on page 14

2.1  Warnings and cautions

To avoid personal injury or property damage, adhere to the safety instructions and information in the 

section Regulatory and Safety Document. 

2.2  Environmental requirements

The front and rear of the system must be clear of any materials that could block or disrupt system airflow. 

Disruption of airflow can cause performance issues or system damage due to overheating. 

2.2.1  Airflow requirements

Use the following guidelines to ensure proper system airflow:

• The airflow in and out of the equipment must not be restricted.
• Controlled air conditioners that are functional and can sufficiently maintain specified system 

operating temperatures should be located in the facility where the system will be installed.

• If rack doors will be used, ensure that the solution used with the system does not prevent airflow from 

the cold aisle from entering the system freely.

2.3  Rack requirements

The ActiveScale P100E3 is installed into a customer-supplied rack. Use the guidelines in this section to 

choose an appropriate rack mounting solution.

Important: 

The absolute minimum depth requirement for the ActiveScale 

P100E3 is 42.12 in (1070 mm). However, Quantum Corporation recommends 

selecting a rack with a minimum depth of 48 in (1200 mm) to allow for proper 

PDU installation and cable routing.

Use the following additional guidelines when choosing a rack mounting solution for the ActiveScale 

P100E3:

Summary of Contents for ActiveScale P100E3

Page 1: ...ActiveScale 6 68926 04 Rev A with ActiveScale OS 6 1 0 software P100E3 Site Requirements Guide...

Page 2: ...gistered trademarks or trademarks of Quantum Corporation and its affiliates in the United States and or other countries All other trademarks are the property of their respective owners Quantum specifi...

Page 3: ...P100E3 site requirements 11 2 1 Warnings and cautions 11 2 2 Environmental requirements 11 2 2 1 Airflow requirements 11 2 3 Rack requirements 11 2 4 Delivery route inspection 12 2 4 1 Walking path i...

Page 4: ...ActiveScale P100E3 Site Requirements Guide 4...

Page 5: ...Guide List of tables 5 List of tables Table 1 1 System specification summary 10 Table 2 1 Footprint of packaging 12 Table 2 3 Space requirement specifications 13 Table 2 2 Footprint of components 13 T...

Page 6: ...ActiveScale P100E3 Site Requirements Guide List of tables 6...

Page 7: ...ActiveScale P100E3 Site Requirements Guide List of figures 7 List of figures Figure 1 1 ActiveScale P100E3 system layout 9 Figure 2 1 Minimum servicing space required 13...

Page 8: ...ActiveScale P100E3 Site Requirements Guide List of figures 8...

Page 9: ...tem needs to make before integrating the system at the site where the system will be deployed This document should be used by the systems architect system planner and site manager and teams which plan...

Page 10: ...irements typical maximum N A 3 node 1 85 to 2 03 kW Relative humidity 20 to 95 non condensing 20 to 80 non condensing Relative humidity gradient 30 per hour maximum 30 per hour maximum System width an...

Page 11: ...ge due to overheating 2 2 1 Airflow requirements Use the following guidelines to ensure proper system airflow The airflow in and out of the equipment must not be restricted Controlled air conditioners...

Page 12: ...path inspection Walking paths must be clear of obstructions and wide enough to allow passage of the packaged system 44 5in x 51in to the location where it will be unpacked The following is a list of o...

Page 13: ...Before moving the system verify that the rack can support the dynamic load of the system weight during movement 2 6 Servicing space requirements Important Mounting a PDU or other equipment vertically...

Page 14: ...cessive current spike created by all the components powering on simultaneously To prevent the potentially negative effects of excessive inrush current on the system Quantum Corporation recommends sele...

Page 15: ...iber These cables must comply with the Ethernet 10GBASE SR standard Ensure that you do not exceed the specified maximum 10GBASE SR cable length for the cable type chosen For example do not exceed a le...

Page 16: ...ActiveScale P100E3 Site Requirements Guide 16...

Page 17: ...ther assistance contact the Quantum Corporation Support Center Region Support Contact North America 1 800 284 5101 toll free 1 720 249 5700 EMEA 1 800 7826 8888 toll free 49 6131 324 185 Asia Pacific...

Reviews: