INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

4

5

1  Introduction

Validity

These instructions are only valid for crystalline solar modules 
from the company Qcells as specified at chapter "2.1 Technical 
specifications"
. Qcells assumes no liability for damage resulting 
from failure to observe these instructions.

  Please observe the wiring and dimensioning of the system.
  The installer of the system is responsible for compliance with 

all necessary safety regulations during set-up and installation.

Qcells assumes no liability on the basis of these instructions. 
Qcells is only liable in the context of contractual agreements or 
in the context of accepted guarantees. Qcells accepts no other 
responsibility for the functionality and safety of the modules.

  Please observe the instructions for any other system compo-

nents that may be part of the complete solar power system. It 
may be necessary to carry out a structural analysis for the en-
tire project.

  If your questions are not satisfactorily answered in the manual, 

please contact your system supplier.

Additional information can be found on our website at 
www.qcells.com.

Information for the Operator

  Please keep this manual for the entire life of the solar power 

system.

  Please contact your system supplier for information concerning 

the formal requirements for solar power systems.

  Please be sure to contact the relevant local authorities and en-

ergy providers regarding regulations and permit requirements 
prior to installation of the solar power system. Your financial 
success depends on the fulfillment of these requirements.

Other applicable documents

This installation manual is only valid in combination with the fol-
lowing technical information.

Document type

Product data sheet

Packaging and transport information

 
MISUSE OR INCORRECT USE OF SOLAR MODULES VOIDS THE 
LIMITED WARRANTY AND MAY CREATE A SAFETY HAZARD 
AND RISK PROPERTY DAMAGE. THIS INCLUDES IMPROPER IN-
STALLATION OR CONFIGURATION, IMPROPER MAINTENANCE, 
UNINTENDED USE, AND UNAUTHORIZED MODIFICATION.

Attention!

This marking indicates that this product should not be disposed 
of with other household waste within the EU. Recycle this product 
properly to prevent possible damage to the environment or a risk 
to human health via uncontrolled waste disposal and in order to 
promote the sustainable reuse of material resources. Please re-
turn your used product to an appropriate collection point or con-
tact the retailer where you purchased this product. Your retailer 
will accept used products and return them to an environmental-
ly-sound recycling facility.

2  Planning

2.1 Technical specifications

For additional information see the relevant datasheet of the module provided at www.qcells.com.

PRODUCT LINE

Q.PEAK DUO XL-G11S.3 / BFG,     Q.PEAK DUO XL-G11S.7 / BFG

Type

Q.ANTUM DUO

Length [in]

96.9 (2462 mm)

Width [in]

44.6 (1134 mm)

Frame height [in]

1.38 (35 mm)

Area [yd²]

3.3 (2.79 m²)

Weight [lbs]

76.9 (34.9 kg)

Max. system voltage V

SYS

1500 V (IEC) / 1500 V (UL)

Max. series fuse rating

25 A

Permissible temperature range

–40 °F to +185 °F (–40 °C to +85 °C)  

Junction box protection class

≥ IP67 with bypass diode

Connector protection class

IP67 or IP68

Fire rating based on ANSI / 
UL 61730

C / TYPE 29 (New Type is similar to Type 3 but with metallic frame)

Max. test load Push / Pull

1

 [lbs/ft²]

113 /50 (5,400 Pa / 2,400 Pa)

Max. design load  
Push / Pull

1

 [lbs/ft²]

75 / 33 (3,600 Pa / 1,600 Pa)

Middle rail

No

Certificates

Quality Controlled PV by TÜV Rheinland; CE-compliant; IEC 61215:2016; 
IEC 61730:2016; PV module classification: Class II;

1

 Test and design load in accordance with IEC 61215:2016, depending on mounting options (see section "2.3 Mounting options")

44.6

"

(1134 mm)

55.1

"

 (1400 mm)

96.9

"

 (2462 mm)

1.38

"

 (35 mm)

4 × Mounting slots (DETAIL A)

Frame

43.0

"

(1092 mm)

Label

4 × Grounding holes,
Ø 0.18

"

 (4.5 mm)

15.7

(400 mm)

8 × Mounting slots system Tracker (DETAIL B)

DETAIL A

0.63

"

 (16 mm)

0.33

"

 (8.5 mm)

0.83" (21

 

mm)

DETAIL B

0.39

"

 (10 mm)

0.28" (7 mm)

0.87" (22

 

mm)

42.9

"

(1090 mm)

31.1

"

 (790 mm)

≥ 13.8

"

 (350

 mm)

≥ 29.5

"

 (750

 mm)

20.9

"

 (531mm)

8 × Drainage holes

0.12 × 0.24

"

 (3 × 6 mm)  

Tracker slot 

Mounting
slots

Fig. 1: 

External dimensions and components for Q.PEAK DUO XL-G11S.3 / BFG, Q.PEAK DUO XL-G11S.7 / BFG.

Summary of Contents for Q.PEAK DUO XL-G11S /BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11S X BFG solar module series...

Page 2: ...ator are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation an...

Page 3: ...AGE THIS INCLUDES IMPROPER IN STALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of...

Page 4: ...Installation using a mounting structure for solar modules Mounting Structure Requirements Requirements for the mounting structure Conform to the necessary structural requirements Compliant with local...

Page 5: ...sult from the safety factor 1 5 Mounting options with clamps The illustrated installation options apply for both horizontal and vertical module orientation Module Clamp Mounting rail 4 CLAMPS ON LONG...

Page 6: ...same material properties Distance between outer edge of module and middle of the clamp 2 Planning 2 3 Mounting options Tracker mounting options Module Bolt Mounting rail TRACKER INSTALLATION USING 15...

Page 7: ...clear ance between the bottom module plane level of bottom frame leg and closest substructure element below solar module lam inate The minimum clearance is defined by the maximum test push load and t...

Page 8: ...gulations when designing the system It has to be ensured that the maximum system voltage including all necessary safety margins is not exceeded Take the voltage limit of the inverter into account when...

Page 9: ...connection cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any ob...

Page 10: ...out work on the inverter and the wiring with extreme cau tion Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the invert...

Page 11: ...ectrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of...

Page 12: ...n inches 0 1 7 7 0 0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are mark...

Page 13: ...installation area alone or without taking ade quate security precautions Please commission a trade specialist NOTE Module surface damage may occur Remove snow and ice carefully without force e g with...

Page 14: ...nstallation manual solar modules Q PEAK DUO XL G11S X BFG_modules_series_2023 10_Rev05_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry...

Reviews: