INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO ML-G10.X – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO ML-G10.X – Q CELLS

13

Module Selection

For detailed key electrical data, please refer to the actual data sheet 
referring to the relevant Module (available at www.q-cells.com).

 

Ä

For maximum energy yields, mismatches of specified electric 
current (I

MPP

) of more than 5 % should be avoided for all modules 

connected in series.

Safety Factor

During normal operation, a module may generate a greater current 
and / or higher voltage than that determined under standardized 
test conditions. Please use a safety factor of 1.25 for the following:

• 

Calculating the voltage measurement values (V

OC

) of components

• 

Calculating the current measurement values (I

SC

) of conductors

• 

Sizing of control systems connected to the outlets of the solar 
modules

 

Ä

Please follow the valid national guidelines for the installation 
of electrical systems.

Series Connection

Connection of modules in series is only permitted up to the 
maximum system voltage as listed in the applicable data sheet 
of all the relevant modules to be installed.

 

Ä

Take into account all possible operating situations and all 
relevant technical norms and regulations when designing the 
system. It has to be ensured that the maximum system voltage, 
including all necessary safety margins, is not exceeded.

 

Ä

Take the voltage limit of the inverter into account when 
determining the maximum number of modules in the string.

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 
(caused by module defects, ground leaks, or defective insulation).

 

Ä

Ensure that the maximum reverse current load capacity 
indicated in the data sheet is met.

In order to limit reverse currents that may occur, we recommend 
using the following safety options:

1) 

Layout with a limited number of 
parallel connected strings :

Without undertaking further current blocking measures, a maximum 
of two module strings may be operated in parallel on a single 
inverter or MPP tracker.

2) 

Layout with string fuses :

Use overcurrent devices (e.g. fuses) according to the relevant 
standards in each string. Use gPV-fuses according to IEC 60269-6. 
Observe the maximum permitted number of strings as indicated 
in the specifications provided by the respective string fuse 
manufacturer and the technical guidelines.

NOTE!

When installing different product versions, the lowest minimum 
permitted reverse current load capacity applies.

Inverters

Inverters with or without transformers may be used.

2  PLANNING

2.4 ELECTRICAL LAYOUT

3  INSTALLATION

3.1  SAFETY AND TRANSPORT

 

Ä

Leave modules in their original packaging until 
installation.

 

Ä

Store the modules securely in cool and dry 
rooms. The packaging is not weatherproof.

 

Ä

Inspect the packaging for damages.

 

Ä

Contact the transport company regarding 
any damage to the packaging and follow their 
instructions.

 

Ä

Follow any instructions on the packaging.

 

Ä

Ensure that all personnel are aware of and 
adhere to accident-prevention and safety 
regulations.

 

Ä

While working wear clean gloves.

§

GB

§

I

§

D

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Do not install damaged modules.

 

Ä

Inform your distributor of any damages 
immediately.

Warning! Fire Risk!

 

Ä

Do not install modules indoors.

 

Ä

Do not install modules on moving objects.

Summary of Contents for Q.PEAK DUO ML-G10.X Series

Page 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO ML G10 X solar module series Valid for Africa Europe LatinAmerica South America...

Page 2: ...nal safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional...

Page 3: ...ements Other applicable documents In addition to this Manual following technical information are relevant DOCUMENT TYPE Product data sheet Packaging and transport information Fig 1 External dimensions...

Page 4: ...r stress free expansion and contraction due to temperature fluctuations Ensure that no additional forces are applied through the mounting system into the module except for the wind and snow loads Addi...

Page 5: ...10 Q PEAK DUO BLK ML G10 Q PEAK DUO ML G10 a Q PEAK DUO ML G10 a Q PEAK DUO BLK ML G10 a Q PEAK DUO BLK ML G10 a INSTALLATION ON MOUNTING POINTS Q PEAK DUO ML G10 Q PEAK DUO ML G10 Q PEAK DUO ML G10 2...

Page 6: ...stability of the mounting system including clamps has to be evaluated by the system supplier The listed test load values have been determined with the following clamp parameters clamp width 40 mm and...

Page 7: ...rrence of reverse currents caused by module defects ground leaks or defective insulation Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit reve...

Page 8: ...Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of...

Page 9: ...result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire open c...

Page 10: ...led personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type and manufacturer Use minimum 4mm2 copper w...

Page 11: ...light concentrators e g mirrors or lenses Ensure that the cabling is not exposed and or hanging and is protected from dirt moisture and mechanical friction 4 ELECTRICAL CONNECTION 4 4 AFTER INSTALLATI...

Page 12: ...w and ice carefully without force e g with a very soft broom Do not scratch off dirt Module cleaning has to be done by qualified personnel according to the state of the art and taking into account all...