NOTE! Damage to the solar modules!
Ä
Ensure voltage-free wiring (comply with bending
radius of ≥ 60 mm).
Ä
Store cable hanging freely. Cables must not lie
between the module and substructure (risk of
crushing).
NOTE! Material damage due to short circuit!
Ä
Only interconnect cables of the same string.
Ä
Take care not to short-circuit the string.
5 ELECTRICAL CONNECTIONS
5.1 SAFETY
EN
click
5 ELECTRICAL CONNECTIONS
5.2 BEFORE INSTALLATION
NOTE! Damage to the solar modules!
Ä
Do not damage the back sheet of the module.
Ä
Remove adhesive tape on the rear.
Ä
Cut through cable clips.
1
Alignment of 60 cell modules:
Ä
Align the solar modules so that all junction boxes
in each string point in the same direction.
Ä
Only solar modules facing in the same direction may be
interconnected in series.
2
Junction
box
Modul
EN
Alignment of 120 cell modules:
Ä
Align the solar modules so that all junction boxes
in each row point in the same direction.
Ä
Depending on the length of the string, observe a 180° string
rotation from row to row.
3
String 1,
Row 1 (East)
180°
180°
180°
180°
180°
180°
String 2,
Row 1 (West)
String 1,
Row 2 (East)
String 2,
Row 2 (West)
+
+
-
-
+
+
-
+
-
+
-
+
-
+
-
+
-
+
-
+
-
-
+
-
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Ä
Ensure the correct module types are used (see
“Module selection" on page 7).
NOTE!
•
The orientation of the modules in the neighbouring
rows must be observed.
Ä
Plan the wiring of the rows before installation so as to ensure
optimal wiring during the installation.
String 1,
Row 1 (East)
180°
180°
180°
180°
180°
180°
String 2,
Row 1 (West)
String 1,
Row 2 (East)
String 2,
Row 2 (West)
+
+
-
+
-
-
+
+
-
+
-
-
-
+
-
+
+
-
+
-
+
+
-
-
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Label
Ä
Depending on the polarity, fasten cables with 2
cable clips each on the long module side.
Ä
Do not fasten cables while live or crosswise.
•
The cables later run to the roof ridge of the Q.FLAT-G5.
4
Ä
Ensure the plugs are firmly connected. The plugs
should audibly snap into place.
Ä
Check the installation dimensions against the
project documents.
Ä
Take corrective action if necessary.
Ä
Connect the system as shown in the project documents.
Aids, tools:
Project documents, layout plan
NOTE! Material damage due to short circuit!
Ä
Make sure that the cable and plug are not lying on
a water-bearing layer, are not touching the roof
cladding and are not rubbing against edges and
components.