4
INSTALLATION DIAGRAM
Section 5
Draw a straight line by a measuring stick starting from the surface of the oven to 700+280: 990 mm if you want to
save a space of 700 mm between the oven and the lower surface of the chimney hood. Align the drawn line to the
right and left edges. Draw a 67,5 mm axis line from aligned center to every two sides. Make a hole by 6 mm
diameter electrical drill through two drawn points. Penetrate the expansion bolt and install the hangers.
Doing installation of secondary chimney of the chimney hood: draw 75 mm line from the top surface towards the
lower section. Make sure that the line is equal to right and left parts. Draw 50 mm line each at both sides of the line
and, then, make a hole through these two lines. Penetrate an 8 mm diameter expansion bolt and tighten until 2 mm
space is left in- between of a 2,5 diameter slat screw and the expansion bolt. Later, the product is mounte
d on its
place and the installation will be completed by installing the inner chimney.
The operation order:
1
st
operation:
Installation of hanger
nd
2 operation:
Installation of chimney connection metal sheet
rd
3 operation:
Hanging the chimney hood
th
4 operation:
Installation of lower chimney of the chimney hood
th
5 operation:
Installation of inner chimney
th
6 operation:
Making electrical connection
INSTALLATION :