11.5 Carrying out commissioning
Begin
start-up?
Expert code:
5000
Runtime and
ClO
2
reset
Really reset runtime
and ClO
2
?
Produce
pre-batch?
Start!
Empty
vessels?
Outlet v. open
- Confirm!
Empty
vessels?
Outlet v.closed
- Confirm!
Emptying
vessels!
05:00 mm:ss
Produce
1st batch?
Start!
1st batch
HCl vessel
NaClO2 vessel
05:23 mm:ss
Pre-batch
HCl vessel
NaClO2 vessel
05:23 mm:ss
Pre-batch
HCl vessel
NaClO2 vessel
Stop pump?
Pre-batch
HCl vessel
NaClO2 vessel
05:23 mm:ss
Operation: 24 h
ClO2: 4 g
Operation: 24 h
ClO2: 4 g
Runtime and
ClO
2
reset
Operation: 0 h
ClO2: 0 g
Operation
B0499
Explanation of the symbols in the menu items "1st Batch"
Symbol
Meaning
Comment
↑
First row:
Pre-storage
vessel full
↓
First row:
Pre-storage
vessel empty
↓
Second/third row:
Level warning
HCl or NaClO
2
drum
Place filled
chemical drums
ready
■
HCl or NaClO
2
measuring vessel
full
□
HCl or NaClO
2
measuring vessel
not full
1.
Check whether a mixer vessel is connected to the outlet valve,
middle left on the mixer vessel.
2.
Lead the PVC tube into a canister of sufficient volume in which a
ClO
2
removal agent has been mixed, see the "Accessories" chapter.
3.
Change to the
‘Begin commissioning?’
setting menu by pressing
the
[Change]
key and press the
[ENTER]
key.