![Pro-dig Intelli-Tork H200 Instruction Manual Download Page 5](http://html1.mh-extra.com/html/pro-dig/intelli-tork-h200/intelli-tork-h200_instruction-manual_1604939005.webp)
WWW.PRO-DIG-USA.COM
785.856.2661
5.
1.
Press to connect and disconnect from the Intelli-Tork (ITK). The icon will turn blue once
connected and data will be displayed. Disconnect when the ITK is no longer in use. This is to be
treated as a power off procedure.
2.
Pause and restart data logging. User must initiate the log from the log configuration screen to
enable this feature.
3.
Exit application and turn off ITK remote.
4. Change screen brightness levels.
5.
Change units (Thrust and Angle can be turned off)
6.
Zero associated readings. (Torque and Thrust should be zeroed at the beginning of each pile
under no load).
7.
Depth, manually increase/decrease depth as pile is driven.
8.
Shows the hub serial number you are currently connected to or the last hub you were
communicating with.
9.
Pile and Job number.
10.
Press to setup Project and Pile Number. Icon will turn blue while logging, select logging icon at
the top of the display to start and stop logging. (Data will append to the file called out in item 9)
11.
Set alarms.
12.
Send all data to the Cloud for automatic processing. (Must be connected to WiFi)
13.
Enter Settings.