INSTALLATION
EATON
Powerware
®
Energy Management System (EMS) Upgrade Kit User’s Guide
S
164201724 Rev 1
www.powerware.com
31
15.
To configure panels and breakers using the software configuration
tool, continue to the following section, Initial Panel and Breaker
Configuration (Using the Software Configuration Tool)."
To configure panels and breakers using the optional display,
continue to Step 16.
16.
Click
Disconnect
to disconnect from the EMS−UGK. Verify that Not
Connected" displays at the bottom of the page.
17.
Close the software configuration tool and remove the configuration
cable.
18.
Activate the reset switch on the bottom of the electronics module:
hold the switch for 10 seconds or until the display (if installed) turns
off, then release the switch.
19.
Continue to Initial Panel and Breaker Configuration (Using the
Display)" on page 34.
Initial Panel and Breaker Configuration (Using the
Software Configuration Tool)
To configure the panels and breakers:
1.
Click the
Panel Config
tab to display the EMS Panel Settings page.
2.
Verify that the
Number of BCM Panels Installed
is correct for your
installation.
If you change the value, click
Save Panel Config
to save the setting to
the EMS−UGK. Depending on communication speed, updates take
effect within 15–20 seconds.
3.
Select the panel number to configure (
Panel Selected
).