Inspect unit frames for structural damage.
Inspect frame hinge points. Apply LPS silicone lubricant (non-flammable)
if required.
Inspect all bolts and fasteners are in place and secure.
Inspect the load straps for damage. Nicks or tears are not acceptable.
Inspect the push button switch and rocker switch for condition and
operation. Make sure the wiring is secure.
Test the battery disconnect switch for operation. Cycle the unit testing for
operation, direction and smoothness.
Check that the toeplate is secure and not bent.
Observe the roller operation in the outer frame
rails. Oil rollers as required.
Ensure the operation manual is readily
available for reference.
PowerMate
®
LiftGate™ Installation & Operation Manual
DAILY MAINTENANCE SCHEDULE
FOR PARTS AND SERVICE CONTACT:
1-800-697-Mate
PN 018820 Rev.D2
Eng. 01/ 10/ 13
8.05