(4)Install And Connect The Case
Inside
wall
Rigid
ductwork
Air
discharge
outlet
Leveling legs
1. Remove the front case panel and pull the unit
out of the case. Place the empty case onto the
platform in the closet with the outdoor side facing
the wall plenum opening. Align the case with
plenum opening and attach.
2.
R
emove the rubble plug from the chassis.
3. Adjust the leveling legs so the case is level
from side to side and from level to 1/4" bubble
tilt to the outdoors.
remove the rubble plug
Secondary 3/4” drain
option. If not used.
seal with a MNPT plug
Primary female
drain fitting 3/4”
Bolt case
to platform
External
drain
OR
Internal
Drain(s)
NOTE: Piping is not
supplied with the unit.
Obtain locally.
4. Using field-supplied screws, bolt the case to the
platform.
5. Connect the internal or external drain(s) as
necessary.
(5a)Install And Ground The Unit
To The Case
.
Unit Installed
Through Front Of Case
1. Slide the back of the unit into the case. Push the
unit all of the way into the case until it stops.
NOTE:
Either of the case sides may be
removed to enable the unit to be
slid into the case.
2. Ground the unit to the case by installing the front
case-to-unit hex-bolt.
Hex bolt