GEO-WAVE CLIMBER HORIZONTAL
Rev C
1249-DDH \-DGH
Page 2 of 6
Deck Top
Top View - Footing Layout
NOTE: Footing Layout is for right hand orientation.
Mirror layout for left hand orientation.
Refer to Top View of Structure for layout orientation
Footing Detail
9 15/16"
253mm
28 1/8"
714mm
Deck Height Table
(X)
Refer To
(Finish Grade)
(Top of Soil)
2b Stone, drain rock
Pea Gravel (for drainage)
Concrete Footing
Optional Filter Fabric Over
(welded 5/8" Rod)
Footing Anchor
Installers Manual
Blocking, See
Undisturbed Soil
27"
*
686mm
18"
457mm
12"
305mm
* Footing Depth must be adjusted to compensate for the
depth/thickness requirements of selected safety
surfacing. See Section 06.1 of the Installation Manual.
Step 1
For Deck to Ground Mount Only.
Dig (2)
12" footing holes. Refer to Footing Layout and Footing Detail below for depth and locations.
IMPORTANT: For areas with soft soil conditions, larger footings may be required
9" Loose Fill Compacted
Protective Surfacing
(shown) See Note D.
Deck Height Table
Geo-Wave Deck to Ground Mount
Deck Height
X (in)
X (mm)
24"
69 7/8
1774
30"
68 1/8
1730
36"
65 3/4
1671
42"
62 11/16
1592
48"
58 13/16
1495
54"
54
1372
60"
47 7/8
1216