Installation of electronic components
4.2 Pulling devicenet cables
The devicenet cables will be pulled through the holes for the satellites. When pulling the
cables it is easiest to start at the top and guide the cables downwards.
1.
Start by pushing a red PlayAlive cable through the satellite hole top, in the left leg.
Push it in an upwards motion so that it will go across the middle pillar and to the satel-
lite hole top in the right leg.
2.
Then push another red PlayAlive cable through the satellite hole
top in the left leg, the same as in point 1. Push the cable trough in a
downwards direction, so that it can be pulled through the satellite hole
middle in the left leg.
3.
Take another red PlayAlive cable and push it through the satellite
hole middle, in the left leg, in a downwards direction so that it can be
pulled out the satellite hole bottom, in the left leg.
See illustration “pulling of devicenet cables” for more guidance.
Once you have completed this repeat point 2 and 3 on the wave’s right
leg.
Notice:
To ensure easy
access and connection to
the game controller and
satellites please make
sure that you keep a
hold of one end of the
cables by the starting
point, to keep it in place
here. Do the same at
the finish point.
This will also prevent the
cables from falling down
through the legs of the
Wave.
Notice:
Point 2 and
3 of this installation
point are symmet-
ric. Therefore, the
procedure is the
same on both sides.
The order the de-
vicenet cables are
pulled in does not
matter, however,
the described order
is recommended.
Satellites
hole top
Satellites
hole middle
Satellites
hole bottom
4.1 Connecting power cable
Once the Wave has been cast and secured the electronics can be
installed.
Start by having an electrician connect the power cable to the
pigtail cable.
Here it is important to keep in mind that the cable should be able
to reach the top of the middle pillar arm, and be operable after-
wards.
Important:
This job
must be performed
by an electrician.
Pulling of devicenet cables.
Satellites
hole top
Satellites
hole middle
Satellites
hole bottom
2 m Play-
Alive cable