Construction
3.1 Overview of construction site
3.2 Prepare for installation
The site for the placement of wave should have a
minimum diameter of 5,3 m.
Note that the Wave should have a power supply of
230 V drawn to the middle pillar. This needs to be
done by an electrician.
Dig a hole for the middle pillar. It should be 0,5 m deep and
have a diameter of 300 mm. Please make sure to align this
with the 230 V power cable.
Once this is done, dig two holes for the legs of the Wave.
The holes should be an ellipse, 300 mm wide and 600 mm
long. The holes should be dug with a tilt of approximately
45°.
The two holes should have a distance of 5,3 m between
them, measured from the center of the holes. Make sure
that the holes are dug 2 m infront of the hole for the middle
pillar. As well as the hole for the middle pillar will be aligned
with the middle between the two holes for the legs. See
illustration “overview of holes placement”.
Please prepare for the following installtion by reading instal-
lation point 7 “Appendix”.
2 m
5,3 m
2,65 m
Important:
when digging the
hole keep in mind the power
cable (230 V) should be pulled
through the middle pillar.
Overview of holes
placement.
3.3 Initial pulling of cables
The purple PlayAlive cable should be pulled now,
before
any asem-
bly is begun.
Push it through the middle pillar arm and upwards, so that the cable
will go through the middle pillar and to its top. Then push it down
through the left leg of the wave, and leave the connector of the
cable outside the hole. See illustration “overview of initial pulling of
devicenet cable”. Please see installation point 3.4 for orientation of
wave left leg and middle pillar.
Please make sure to leave the connectors of the cable outside the
holes and that they stay there doring the next steps of the installa-
tion process.
Also note that this step
is only performed once,
on the left side of the
wave.
Important:
Make
sure that the connec-
tors of the cables are
left outside the pillars
throughout the entire
assembly process, so
that they won’t be
lost inside the pillars.
Important:
If this step is
not completed
know step 4.2
and 4.3 will be
very difficult to
complete.
Overview of initial pulling
of devicenet cable.
Satellites
hole bottom
Middle
pillar arm
Notice:
This installa-
tion step is only per-
formed once, on the
left side of the Wave.
300 mm
300 mm
600 mm
5,3 m
5,5 m Play-
Alive cable
Notice:
When pulling
this cable it can be help-
ful to use a pulling string.