37
Connection diagram, series connection
Actuator
Actuator
Control System
Evaluation Device
Receiver 1
Actuator
Receiver 2
Receiver n
Ex area
Non-Ex area
FS: Fail-Safe
S21
S11
12
A1
A2
22
0 V
24 V
A1
A2
A1
A2
A1
A2
12
22
12
22
S21
S11
S21
S11
Y32
Y32
Y32
I1 (FS)
I2 (FS)
I1
I2
I3
CAUTION!
Extension of delay-on de-energisation
When several (n) devices are connected in series, the delay-on de-ener-
gisation time adds with the number of interconnected safety switches.
The may. delay-on de-energisation is composed of
max. delay-on de-energisation actuator
+ (n-1) x max. delay-on de-energisation of the inputs
+ delay-on de-energisation of the evaluation device
Suitable Pilz evaluation devices are, for example:
}
PNOZelog for safety gate monitoring
}
PNOZpower for safety gate monitoring
}
PNOZsigma for safety gate monitoring
}
PNOZ X for safety gate monitoring
PSEN cs1.13p ATEX
Operating Manual PSEN cs1.13p ATEX
21097-2EN-13