6.0 

MAINTENANCE 

 

6.1 

GENERAL 

 

Maintenance, inspection and operation activities have to be carried out 
in compliance with the regulations in force on the matter in the place of 
installation  of  the  equipment  (type  and  frequency).  Before  performing 
any kind of intervention, it is important to make sure that the device has 
been  closed  at  inlet  and  outlet  and  that  the  pressure  has  been 
discharged  from  the  piping  between  the  valve  and  the  cut-off  valves. 
Maintenance  interventions  are  strictly  bound  to  the  quality  of  the 
conveyed  gas  (impurities,  humidity,  gasoline,  corrosive  substances) 
and to the filtration efficiency. 
Therefore,  it  is  always  recommended  to  perform  preventive 
maintenance  interventions  whose  frequency  shall  be  determined 
according  to  the  following  aspects,  unless  specified  by  regulations 
already in force: 

the quality of the conveyed gas; 

the cleanness and preservation status of the piping upstream of 
the regulator: in general, for example, after the first start of the 
plants, more frequent maintenance interventions are required if 
the internal cleanness of the piping is precarious. 

the reliability level required from the plant. 

 
Before starting disassembling the equipment make sure: 

to  have  a  series  of  original  spare  parts  available.  Spare  parts 
shall  be  original  spare  parts  by  Pietro  Fiorentini;  consider  that 
the most important parts such as membranes are marked. 

to have a series of wrenches as shown in table 10. 

 
For  a  correct  maintenance,  suggested  spare  parts  are  unmistakably 
identified by means of tags bearing the following information: 

the  SR  layout  drawing  number  of  the  equipment  in  which  they 
can be used; 

The position given on the SR layout drawing of the equipment; 

It  is  suggested  to  replace  all  rubber  parts;  for  this  purpose,  use  the 
suitable spare part kit as highlighted in Fig. 12, 13, 14.   
 

NB.

 The use of not original parts relieves Pietro Fiorentini S.p.A. from 

any responsibility. 
 
The  depressurization  procedure  shall  occur  paying  attention  to 
discharge  the  drains  into  a  safe  area;  to  avoid  risks  related  to  the 
formation  of  sparks  due  to  bumps  of  impurity  particles  inside  the 
discharge  lines,  it  is  recommended  to  keep  fluid  speed  lower  than  5 
m/sec. 
Moreover,  it  is  suggested  to  perform  reference  marks  on  the  parts 
before disassembling those parts that can be positioned or oriented in 
more than one way during re-assembly. 
Finally, it shall be underlined that O-rings and sliding mechanical parts 
(stems, etc.) have to be lubricated before reassembling them, applying 
a thin layer of silicone grease. Before commissioning, it is necessary to 
verify the external tightness of the equipment at a suitable pressure for 
assuring the absence of external leaks.  

 
 
 
 
 
 

6.2 

MAINTENANCE PROCEDURE FOR THE 

SLAM-SHUT VALVE SBC 187 

 

PROGRAMMED PREVENTIVE MAINTENANCE 

 

Procedure for disassembling, completely replacing the spare parts 
and reassembling the valve SBC 187.

 

 

PRELIMINARY OPERATIONS 

 

A) 

Shut off the valves upstream and downstream of the system and open 
the drain cock carefully. 

 

B) 

Make sure that the pressure upstream and downstream of the device is 
equal  to zero. 

Summary of Contents for MT-188-E

Page 1: ...SBC 187 MT 188 E ENGLISH SLAM SHUT VALVE TECHNICAL MANUAL INSTRUCTIONS FOR THE INSTALLATION COMMISSIONING AND MAINTENANCE ...

Page 2: ...Technical Manual MT 188 E 1 SBC 187 ...

Page 3: ...lly the paragraphs 6 2 7 5 2 7 7 and 9 3 of the standard EN 12186 and 6 2 7 4 7 6 and 9 3 of the standard EN 12279 must be observed The installation in compliance with such standards minimizes the risk of fire and the formation of potentially hazardous atmospheres The equipment is not provided with internal pressure limitation devices therefore it must be installed making sure that the operating p...

Page 4: ... ACCESSORIES 7 3 1 PUSH THREE WAYSWITCHVALVE 7 4 0 COMMISSIONING 7 4 1 GENERAL 7 4 2 GASFEEDING CHECKOFTIGHTNESS CALIBRATIONS 8 4 3 CALIBRATIONCHECK 8 5 0 TROUBLESHOOTING 9 5 1 SLAM SHUTVALVESBC187 TAB2 9 6 0 MAINTENANCE 10 6 1 GENERAL 10 6 2 MAINTENANCEPROCEDURE 10 7 0 FINAL OPERATIONS 13 7 1 CHECKOFTIGHTNESSANDCALIBRATIONS 13 7 2 COMMISSIONING 13 INDEX ...

Page 5: ...essure decrease External manual bypass by means of a hand wheel to obtain pressure balancing and ease the restoration of the device Manual tripping control by means of push button 1 2 OPERATION OF THE VALVE SBC 187 Fig 1 The slam shut device consists of an obturator A a control head B a lever mechanism system for the release C and a restoration system D controlled manually through the lever Fig 1 ...

Page 6: ...wn 15 40 3 8 13 103MH 2700980 Blue 35 3 2700985 Brown 40 3 13 1 19 2700985 Brown 40 3 2702280 White Red 35 60 5 5 15 30 104M 2702454 Fuchsia 70 6 30 1 45 2700713 Green 15 40 2 3 1 6 3 104M 2700750 Black 40 2 5 3 1 8 2700985 Brown 40 3 8 1 18 2700985 Brown 15 40 3 18 30 104MH 2700980 Blue 35 3 2700985 Brown 40 3 30 1 41 2700985 Brown 40 3 2702280 White Red 35 60 5 5 30 60 2702454 Fuchsia 70 6 60 1 ...

Page 7: ... downstream impulse circuit is connected to a straight section of the downstream piping having a length complying to Fig 5 therefore without any signal turbulence as well as that the maximum gas speedattheconnectionpointdoesnotexceed30m sec In order to avoid deposits of impurities and condensate in the pressure feeding connectionpiping provideforthefollowing a The piping shall always be positioned...

Page 8: ...and the head of the safety device is restored automatically thus avoiding the on off switching of the device which may happen due to a sheer oversight if the three way valve is of the normal type with manual operation As a consequence the Push device is a second safety device which assures the non exclusion of the main safety device and allows its periodical check 4 0 COMMISSIONING 4 1 GENERAL Aft...

Page 9: ...ny are closed and that the gas has such a temperature as not to create malfunctions 4 3 CALIBRATION CHECK Check and record the tripping of the slam shut device as follows A For the slam shut devices connected to the downstream piping through the push three way switch valve proceed as follows Fig 10 Fig 10 connect to the way C a controlled auxiliary pressure restore the slam shut device by means of...

Page 10: ...n Replacement O ring pos 15 fig 13 of the obturator gasket pos 1 fig 12 worn Replacement Valve seat Pos 4 Fig 12 eroded or scratched Cleaning Replacement Wrong release pressure Wrong calibration of the min and or max pressure spring Recalibrate acting on the ring nuts Lever mechanisms subject to friction Replace the release device casing It is not possible to perform restoration The cause which le...

Page 11: ... table 10 For a correct maintenance suggested spare parts are unmistakably identified by means of tags bearing the following information the SR layout drawing number of the equipment in which they can be used The position given on the SR layout drawing of the equipment It is suggested to replace all rubber parts for this purpose use the suitable spare part kit as highlighted in Fig 12 13 14 NB The...

Page 12: ...Technical Manual MT 188 E 11 FIG 12 ...

Page 13: ...Technical Manual MT 188 E 12 Position indicator Fig 13 position indicator ...

Page 14: ...Technical Manual MT 188 E 13 Fig 14 Spring for minimum pressure 20 ...

Page 15: ...bed for disassemblyinreverseorder Before reassembling the tightness elements O rings membranes etc it is necessarytochecktheirintegrityand ifnecessary replacethem Once again pay utmost care while handling the valve seat pos 4 Fig 12 in order nottodamagethesealingedges 7 0 FINAL OPERATIONS 7 1 CHECK OF TIGHTNESS AND CALIBRATIONS 1 Open very slowly the on off valve positioned upstream of the slam sh...

Page 16: ...AINTAINING SBC 187 Combined wrench Adjustable spanner Double polygonal box spanner Wr 8 9 10 11 12 13 17 18 19 20 21 24 41 L 300 Wr 10 27 Hexagon Allen wrench Philips screwdriver Flat blade screwdriver Wr 2 3 4 5 6 8 10 6 5 x 100 Pliers for rings 19 40 ...

Page 17: ...Pietro Fiorentini S p A via E Fermi 8 10 I 36057 Arcugnano VI Italy Phone 39 0444 968511 Fax 39 0444 960468 www fiorentini com MT188 E October 2008 ...

Reviews: