background image

Technical manual 

MT 208-E

 

12 

 

5.2 

GAS INPUT, CONTROL OF EXTERNAL 
TIGHTNESS AND SETTING 

 

The pressurization of the equipment shall be performed very slowly. 
Should not any stabilization procedure be carried out, it is 
recommended to keep gas speed in the feeding piping at a value equal 
to 5 m/sec during pressurization. 
To protect the apparatus from damage, the following operations must 
never be carried out: 

ƒ

 

Pressurization through a valve located downstream from the 
apparatus itself. 

ƒ

 

Depressurization through a valve located upstream from the 
apparatus itself. 

External tightness is guaranteed if no bubbles form when a foam 
medium is applied on the element under pressure. 
The regulator and any other apparatuses (slam-shut, monitor) are 
normally supplied already set for the desired set-point. It is possible for 
various reasons (e.g., vibration during transport) for the settings to be 
changed while remaining within the values permitted by the springs 
used. 
We therefore recommend checking the settings using the procedures 
illustrated below. 
Table 6 gives the recommended set-point for the apparatuses in the 
various installation arrangements. The figures in these tables can be 
useful both when checking existing set-point and for modifying them 
should this become necessary later.  
In installation consisting of two lines, we suggest commissioning one 
line at a time, starting from the one with the lover set-point, known as 
the “reserve” line. The set-point of the apparatuses in the line will 
obviously deviate from those specified in the table 6. 
Before commissioning the regulator you must check that all the on/off 
valves (inlet, outlet, any by-pass) are closed and that the gas is at a 
temperature which will not lead to malfunction. 
 

 

5.3 

COMMISSIONING THE REGULATOR 
(fig.19) 

 

If there is also a relief valve in the line, refer to par. 3.1 to check it. 
 
 
 

 

 
 
 
1) 

Partially open the atmosphere drain tap 

6

2) 

Open the AR100 

2

 valve in position 

8

3) 

Open the inlet on-off valve 

V1

 very slowly. 

4) 

By means of the pressure gauge 

5

, check that the pressure 

does not exceed the maximum value permitted by the setting 
spring fitted in the pilot. If necessary suspend the operation by 
closing 

V1

 and completely reduce the load of the spring by 

turning screw 

1

0 anticlockwise (fig. 24). Reopen valve 

V1

slowly. 

 

5) 

Choke the AR100 valve. 

6)     Adjust the setting by alternately adjusting the AR100 valve and 

the 30./... pilot so that the value of the set pressure is obtained 
with the minimum opening possible of the AR100 valve; then 
block the screw 

10

 of the pilot with the provided nut 

9

7)  Close the bleed cock 

6

 and check that the downstream 

pressure, after a period of increase, stabilizes and at a value 
slightly higher than that of closure of the pilot/regulator 
combination. Otherwise eliminate the causes of the internal 
leakage. 

8) 

Using a foam substance, check the tightness of all the joints 
between the on-off valves 

V1

and 

V2

9) 

Very slowly open the downstream on-off valve 

V2

 to obtain the 

complete filling of the pipe. If

 

at the beginning of this operation 

the pressure in the pipe is much lower than the set point, the 
opening of this valve should be choked so as not to go beyond 
the maximum flow rate value for the installation. 

10)  If pumping phenomena arise in normal working conditions, it is 

necessary to repeat the operations in point 

6

 so as to readjust 

the setting, increasing the opening of the AR100 valve. If on the 
other hand, there is an excessive reduction of the regulated 
pressure with an increase in flow, repeat the above operations 
with a smaller opening of the AR100 valve. 

 
 

 

5.4  COMMISSIONING THE REGULATOR 

APERFLUX 101 WITH APERFLUX 101 IN 
LINE MONITOR (fig.20) 

 

 

 

 
 

1) 

Partially open the atmosphere drain tap 

6

2) 

Open the AR100 

9

 valve of the monitor in position 

8

3) 

Close the AR100 

valve of the service regulator in position 1. 

4) 

Open the inlet on-off valve 

V1

 very slowly. 

5) 

Completely increase the setting of the pilot 

3

6) 

Check, via pressure gauge 

5

, that downstream pressure gets 

stabilized at the envisaged monitor setting value. Adjust it acting 
alternatively on regulation bolt of the pilot 

10

 and on regulation 

valve AR100 

9

,

 

so that the setting pressure is the pressure 

reached with the minimal opening possible of the valve AR100. 

7) 

Open valve AR100 

2

 of the main regulator in position 

8

8) 

Slowly decrease the setting of the pilot 

3

 until the chosen value 

for the functioning regulator is reached. 

9) 

Repeat the operations in point 

6

 for the pilot 

and the valve 

2

10)  Wait until the downstream pressure settles at the envisaged 

value and adjust it as descrbed in point 

6

11)  Close the atmosphere drain tap 

6

 and check that downstream 

pressure, after an increase - stage, gets stabilized at a value 
slightly higher than the closure value of the pilot / monitor 

fig. 20 

fig. 19 

                                 | [email protected] | Phone: 877.566.3837 | Fax: 925.407.2903

Summary of Contents for APERFLUX 101

Page 1: ...Aperflux MT 208 E ENGLISH PRESSURE REGULATOR TECHNICAL MANUAL INSTALLATION COMMISSIONING AND MAINTENANCE INSTRUCTIONS sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 2: ...Technical manual MT 208 E 1 INLET PRESSURE OUTLET PRESSURE CONTROLPRESSURE Pressure Regulator sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 3: ...n force in the place of installation or at lease in compliance with standards EN 12186 or EN 12279 In detail it is necessary to meet the provisions of paragraphs 6 2 7 5 2 7 7 9 3 of the standard EN 1...

Page 4: ...INPUT CONTROLLOFEXTERNALTIGHTNESS ANDSETTING 12 5 3 COMMISSIONINGTHEREGULATOR 12 5 4 COMMISSIONINGTHEREGULATOR APERFLUX101 PLUSAPERFLUX101IN LINEMONITOR 12 5 5 COMMISSIONINGTHEREGULATORAPERFLUX101 PLU...

Page 5: ...rust deriving from the control pressure Pc in the control chamber A and the weight of the mobile assembly upwards the thrusts deriving from the upstream pressure Pu the downstream pressure Pd and the...

Page 6: ...rom 20 to 60 bar 290 to 870 2 psig 307 setting range Wd from 41 to 74 bar 594 6 to 1073 3 psig Pilots may be adjusted manually or remotely as shown in table 1 Table 1 Pilot adjusting instructions Pilo...

Page 7: ...PRING CHARACTERISTICS PILOT 304 A Code Color De Lo d Setting range bar 2702290 RED 35 100 5 5 7 10 2702460 GREEN 35 100 6 10 15 2702660 BLACK 35 100 6 5 15 22 2702820 BLUE 35 100 7 22 33 2703045 BROWN...

Page 8: ...f supporting the weight of the regulator the inlet outlet flanges of the piping are parallel the inlet outlet flanges of the regulator are clean and the regulator itself has not been subject to damage...

Page 9: ...ven in fig 7 and 8 positioning and tab 5 speed When the regulator is used in gas pressure reduction stations it must be installed at least according to the requirements envisaged in EN 12186 standards...

Page 10: ...ed below with reference to the valve VS AM 65 fig 10 It is based on the contrast between the thrust on the diaphragm 24 deriving from the pressure of the gas to control and the thrust from the setting...

Page 11: ...resetting system which is controlled manually by the lever C The pressure in the circuit to control acts on the diaphragm in the control head B This diaphragm which is integral with a control rod D re...

Page 12: ...ich the body and its inner metallic partition walls are designed in accordance with the strength requirements in this document Wds setting range of the pressure regulator which can be obtained using t...

Page 13: ...ust the setting by alternately adjusting the AR100 valve and the 30 pilot so that the value of the set pressure is obtained with the minimum opening possible of the AR100 valve then block the screw 10...

Page 14: ...operations at least 2 3 times B On devices without the push valve fig 23 we recommend connecting the control head separately to a controlled auxiliary pressure and repeat the operations described abov...

Page 15: ...nitor Slam shut Relief valves Reg set point Pds bar Monitor Set point Accelerator Set point Relief valve Set point Slam shut Max Set point Slam shut Min Set point 0 8 Pds 2 1 Pds x 1 1 Pds x 1 2 Pds x...

Page 16: ...8 29 PROBLEM POSSIBLE CAUSE APPARATUS REMEDY Valve seat 2 damaged Replace Diaphragm 3 damaged Replace O ring 13 damaged Replace Dirt or foreign bodies in the sealing area Regutator fig 25 Clean Obtura...

Page 17: ...ch as diaphragms are marked a set of wrenches is available as specified in table 8 For a proper maintenance the recommended spare parts are unequivocally identified by labels indicating the No of asse...

Page 18: ...he high cap 5 from the main body 1 4 Remove the high cap 5 5 Take out the diaphragm group and separate the single parts 3 9 and 11 6 Remove the grill from the body 1 7 Remove the O Ring 13 from the gr...

Page 19: ...place them Check the good conditions of the grill 7 4 DISASSEMBLING UNIT 302 A PILOT A Separate the flow regulation valve AR 100 from the pilot 7 4 1 PILOT 302 A fig 26 1 Loosen the blocking nut and u...

Page 20: ...Remove the nut together with the disc and the diaphragm 8 Loosen and remove the fixing bolts of the head cap to the flange 9 Remove the head cap 10 Remove the spring and the diaphragm 11 Remove the ri...

Page 21: ...ve the flange from the valve body 14 Unscrew the diaphragm support 15 Remove the diaphragm support together with the spring and remove the o rings 16 Remove the obturator together with the spring and...

Page 22: ...8 29 50 51 52 O ring 22 Carefully check the good conditions of the valve seat and particularly of the modular piston 23 Replace all components being part of the Replacement Kit To reassemble the pilot...

Page 23: ...ion valve AR 100 from the pilot 7 5 1 PILOT 304 A fig 27 1 Loosen the blocking nut and unscrew completely the pilot regulation bolt 2 Unscrew the cap 3 Remove the cap together with the spring and the...

Page 24: ...nd the diaphragm 8 Loosen and remove the fixing bolts of the head cap to the flange 9 Remove the head cap together with the spring 10 Unscrew the diaphragm support 11 Remove the obturator support toge...

Page 25: ...roup fitting 14 Unscrew and remove the fixing nut of the valve seat group to the valve body 15 Separate the valve seat group from the valve body and the diaphragm support 16 Unscrew the valve seat fro...

Page 26: ...t you can run the other way around the operations described for the disassembling process Peculiar Notes A In disassembling and reassembling the valve seat group please ensure that the valve seat does...

Page 27: ...ts 5 Remove the bolts from the body 6 Remove the O rings 7 Replace al components being parts of the Replacement kit To reassemble the valve you can run described operations the other way around sales...

Page 28: ...Technical manual MT 208 E 27 fig 25 Aperflux101 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 29: ...Technical manual MT 208 E 28 PILOT 302 A fig 26 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 30: ...Technical manual MT 208 E 29 Unit A Diaphragm Unit B Valve Unit C Obturator sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 31: ...Technical manual MT 208 E 30 PILOT 304 A 305 A fig 27 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 32: ...Technical manual MT 208 E 31 Unit A Obturator Unit B Valve sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 33: ...Technical manual MT 208 E 32 fig 28 PILOT 307 A sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 34: ...Technical manual MT 208 E 33 Unit B Valve Unit A Obturator sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 35: ...Technical manual MT 208 E 34 AR 100 fig 29 sales mvandc com Phone 877 566 3837 Fax 925 407 2903...

Page 36: ...e downstream from the regulator to create a small gas flow 4 Fix the pilot regulation bolt until the desired set point value is reached 5 Close the bleed cock to the atmosphere 8 2 START UP 1 Very slo...

Page 37: ...l 39 02 696 14 21 Fax 39 02 688 04 57 Pietro Fiorentini S p A via E Fermi 8 10 I 36057 Arcugnano VI Italy Tel 39 0444 968 511 Fax 39 0444 960 468 www fiorentini com MT208 E January 2010 sales mvandc c...

Reviews: