Figure 5A Typical Wiring Diagram for S89F with Direct Spark Ignition
6
WIRING
6.1
Refer to wiring diagram shipped with burner and typical wiring diagrams Figures 5 and 5A. The
two power leads (black and white) are located inside the burner panel.
6.2
Electrical installation must be made in accordance with the NEC NFPA 70 or Canadian Electrical
Code, Part 1 and applicable local codes. If this burner is part of a boiler or furnace package
system, check wiring diagram as supplied by the boiler or furnace manufacturer.
7
START UP
7.1
Before attempting a burner start up,
please review the MART Operator's Manuel for recommend setting
and flue requirements
. Also this manual will provide information about the exact sequence of
operation and all other details on the specific Primary Safety Control System being used. This
information will be found in bulletins supplied with the burner, as well as technical bulletins covering other
components. All of these materials should be used as reference in burner start up and service.
7.2
Check boiler water level (if applicable).
7.3
Lay out combustion test equipment (see Section 8.3).
7.4
Attach gas pressure gauge or manometer to upstream side of main gas cock (0-35” w.c.) and to orifice
pressure tap (0-10” w.c.) as well as to pilot gas pressure test tee tapping (0-10” w.c.).
7.5
Check the voltage at the disconnect switch to make certain that it matches that indicated on the burner
label.
7.6
Ensure that all dampers in the flue or stack are fully open.
7
Summary of Contents for X4-400
Page 1: ...X4 AND X4M INSTALLATION AND OPERATION MANUAL ...
Page 4: ......
Page 17: ...X4M 14 ...
Page 18: ...15 ...
Page 20: ...Figure 11A Typical Wiring Diagram For X4M Figure 11B General Arrangement Diagram for X4M 17 ...