Permagard PermaSEAL Installation And Operation Manuallines Download Page 7

Page | 7 
 

We recommend that the discharge pipe work is 50mm solvent welded Class E PVC pressure pipe. To connect the 
discharge pipe work to the discharge spigot on the tank you must firstly screw on the Plain/Threaded PVC Socket 
(supplied already attached) onto the spigot which will then leave you with a plain socket to solvent weld your 
discharge pipe work into. 
 

To conform with current building regulations, low voltage wiring should not use the same conduit as high 
voltage therefore we suggest cutting two 32mm holes to accommodate 32mm conduit into which the pump(s) 
high voltage electrical connections should run in one and the High Level Alarms low voltage cable can run in 
the other.  

 

It is advisable to run the Pump(s) and High Water Level Alarm cable through the 32mm conduit at this stage. If 
the Pump(s) and Alarm are not on site, run a pull cable through the two conduits ready for pulling through the 
cables when they are ready to be fitted.  
 
PLEASE NOTE: We suggest that the pump(s) are removed from the sump before backfilling with concrete. 

 
7.

 

In all applications the tank must be backfilled with a mass concrete mix of a minimum 100mm thickness and 
used in accordance with the ground conditions ensuring that it is as dry as practical to prevent additional 
floatation pressures being exerted on the tank. 
 
The tank MUST be ballasted with water at the same rate as backfilling such that the level difference between the 
water and the backfill does not exceed 150mm at any time. Please ensure that when pouring the concrete 
backfill, suitable steps are taken to prevent the concrete from entering the tank and drainage channel. 

 
8.

 

Where groundwater is present in the excavation, local de-watering of the ground must be undertaken 
throughout the installation procedure until the backfill has fully cured. Please note that the ballast water inside 
the tank should not be removed until the backfill has fully cured. 

 
9.

 

It is extremely important that once the tank has been installed and all the inlet connections made, before the 
pump is installed and run, the system is flushed through and all sand, silt, rubble and general debris removed 
from the tank. 

FAILURE TO DO THIS WILL INVALIDATE THE WARRANTY ON THE PUMP (S).

 

 
10.

 

Once the tank is in position and the discharge pipe work is in place, you must connect the pump to the discharge 
line. Simply screw the non return valve and 50mm waste pipe into the pump then connect the female end to the 
inline shut off valve. 

 

Electrical Connection 

A qualified person in accordance with the Institute of Electrical Engineers Regulations should connect the unit 
to the mains supply taking into account all the electrical information provided. 

 
1.

 

The pump should be connected to a 230V 5A fused spur. 

2.

 

To conform with current building regulations, low voltage wiring should not use the same conduit as high 
voltage. This means the alarm float switch cable should NOT be in the same conduit as the 230V pump cable. 

3.

 

Please ensure that there is suitable slack on the cable to allow for the pump to be removed for maintenance. 

 

High Level Alarm 

 

Please see separate installation notes. 

 
 
 
 
 
 

Summary of Contents for PermaSEAL

Page 1: ...Page 1 BASEMENT SUMP AND PUMP SYSTEM Installation and Operation Guidelines...

Page 2: ...Page 2 Contents 1 Product Summary 03 2 Installation Guidelines 03 3 Technical Specification 08 4 Dimensions 08 5 Parts List 08 6 Maintenance 09 7 Health and Safety 09 8 Guarantee 10...

Page 3: ...or to work commencing The tank is manufactured from polyethylene and as such is extremely robust However as with any preformed tank they are susceptible to floatation and hydrostatic pressures exerted...

Page 4: ...e pump s are set up with the waste pipework float arms and alarm outside of the sump chamber to ensure correct fitting For the single pump system please follow this set up 1 Use PTFE tape around the t...

Page 5: ...ion firmly 2 For both the master and the backup mount the float arm onto the waste pipe using the jubilee clip As per fig 1 3 At this point both pumps will activate at the same time as both float arms...

Page 6: ...tion setting levels may need to be finely tuned when the pumps are in the chamber and water levels can be tested Once the pump or pumps are set up the internal waste pipe connections can be made Simpl...

Page 7: ...not exceed 150mm at any time Please ensure that when pouring the concrete backfill suitable steps are taken to prevent the concrete from entering the tank and drainage channel 8 Where groundwater is p...

Page 8: ...Parts List Locked Sealed Lid Frame with 46mm recess One or two CP 250 Pumps 50mm pressure rated pipe work including a shut off valve and non return pump connection Single pump systems have a single i...

Page 9: ...systems must be vaccinated against diseases to which they may be exposed A first aid kit must be close to hand Note that special rules apply to installations in an explosive atmosphere Special note s...

Page 10: ...placing the defective part at the company s premises inside normal working hours We exclude all liability for any consequential or other damage or losses which may occur We will not be liable if the p...

Reviews: