background image

  

I   ©2019 Pentair plc.

Pentair Pentek Solar Drive Installation Requirements

Once the Pentair Pentek Solar Drive is installed in a shaded location (see Figure 3), it can be wired to DC 
(solar) sources. Maximum cable lengths for 115 and 230Vac for different motor load currents are shown in  
Figure 2 below.

This unit was evaluated for temperature rating of 60/75°C  (140/167˚F) on power field wiring terminals.

Motor 

Load [A]

Nominal 

Voltage [V]

AWG Copper Wire Sizes 

90˚C (194˚F) insulation [ft]

16

14

12

10

8

3.5

115

125

180

300

450

700

230

250

360

600

900

1400

4.5

115

100

150

250

350

500

230

200

300

500

700

1000

5.5

115

80

125

200

300

450

230

160

250

400

600

900

7

115

65

95

150

230

350

230

130

190

300

460

700

IMPORTANT:  Use copper conductors only!

Figure 2: Maximum Input Cable Lengths in Feet (based on 3% voltage drop)

Dimensions of the Pentair Pentek Solar Drive and back panel are shown in Figure 4, with additional 
details on how to mount the unit on page 7.

The Pentair Pentek Solar Drive must be installed in a shaded location, away from any source of heat 
and in an area free of vegetation. Measures must also be made to protect the unit from damage by 
unauthorized persons, large animals, overgrowth, flooding, or other harm.

  WARNING

The Pentair Pentek Solar Drive has voltages capable of causing severe injury or death by electrical 
shock. It should only be installed and serviced by Pentair authorized suppliers, dealers and installers. 

  –  Contact your Pentair Supplier/Dealer for any service or warranty claims
  –  NEC codes take precedence over suggestions in this manual
  –   We strongly recommend that the installation data be recorded into the “Installation Notes” section 

on page 14 and that the manual is stored near the unit

The Pentair Pentek Solar Drive should be mounted at least 2 feet (60cm) above the ground when possible. 
A minimum of 10 inches (25cm) of clearance above the Pentair Pentek Solar Drive is required for internal 
access. There must be no obstruction of air flow to the heat sink. A typical installation on an array 
structure is shown in Figure 3, below.

Figure 3: Pentair Pentek Solar Drive Mounting

Figure 4: Pentair Pentek Solar Drive Dimensions

24”

10”

Solar PV Rack

Solar PV Panel

3”

4.25”

5.5”

4”

10”

Summary of Contents for Pentek PSD15

Page 1: ...pentair com P1061 03 06 19 INSTALLATIONAND OPERATIONMANUAL SOLARDRIVEPSD15 PENTEK...

Page 2: ...e Installation Requirements 6 Pentair Pentek Solar Drive Hardware 7 Pentair Pentek Solar Drive Overview 8 Pentair Pentek Solar Drive Wiring Instructions 9 Pentair Pentek Solar Drive DIP Switch Setting...

Page 3: ...tage with a voltage tester NEVER connect power wiring to Drive before mounting the box NEVER handle or service Drive with wet or damp hands Always make sure hands are dry before working on Drive NEVER...

Page 4: ...ram for a Pentair Pentek Solar Drive operated solar water pumping system is shown in Figure 1 The solar PV array must be connected to an external DC Disconnect and then to the Pentair Pentek Solar Dri...

Page 5: ...oes not provide branch circuit protection Branch circuit protection must be provided in accordance with the National Electrical Code and any additional local codes ELECTRICAL MECHANICAL Solar PV open...

Page 6: ...n a shaded location away from any source of heat and in an area free of vegetation Measures must also be made to protect the unit from damage by unauthorized persons large animals overgrowth flooding...

Page 7: ...Drive controller should be mounted on a wall or other vertical surface using the back bracket see Figure 5 below On the back side of the unit there are two set screws used to hang the unit on the back...

Page 8: ...e enclosure is open there are three terminal blocks 1 Solar PV wires 2 Motor pump wires 3 Pump or tank sensor wires More information about sensor wiring and DIP switches is provided on page 8 Figure 6...

Page 9: ...ugh the right gland float switch signal wires feed through the middle gland and motor load wires feed through the left gland When all conductors are wired into the controller the cover door should be...

Page 10: ...ed on the motor pump and controller combination being used The default value of RMS current when both switches are OFF is 7A for three phase DIP switches 4 and 5 are to be used to match or exceed the...

Page 11: ...xample of how tank and well switch signals can be used with a digital input port is shown in Figure 10 For a tank application if the active wire is connected to Position 1 and the return wire usually...

Page 12: ...sition All LEDs will light up and after a few seconds the Pentair Pentek Solar Drive will try to start the pump indicated by a blinking green light and upon starting the green LED will remain ON 4 If...

Page 13: ...ugh solar production from the solar panels the yellow LED will start blinking again Shutdown To stop the Pentair Pentek Solar Drive s operation the DC Disconnect should be used Once in the OFF positio...

Page 14: ...PV Panel Manufacturer Model Number _____________________________________________ No of Solar PV Panels in Series ____________________________________________________ Note to Installer Record the data...

Page 15: ...e is turned OFF as a result of input from one Mode or more external sensors that are connected to the digital input Over Temperature Pentair Pentek Solar Drive stops operation when the temperature Mod...

Page 16: ...pping charges associated with this warranty and must request warranty service through the installing dealer as soon as a problem is discovered No request for service will be accepted if received after...

Reviews: