The Plancofix can also be installed in front of, or adjacent to, 

the shower. In this case, the shower is connected to one of the 
inlet connections at the side with a DN50 pipe socket. 

To  reduce  odours,  please  fit  the  rubber  flap  (Plancofix  plus) 

provided.

NOTICE!

 If it is installed outside the shower, the tileable cover 

must be used. If the drain cover is used, a slight discharge of 
water is possible.

Inserting the tank

NOTICE!

 The protective covers at the side and the top must be 

fitted to the Plancofix. 

1. Screw on the four feet.
2.

Adjust the feet until the Plancofix is level and is standing in 

the recess at the appropriate height.

3. To reduce the transmission of sounds to a minimum, the

protective cover at the side of the tank must remain in
place.

4. The following materials are approved for the pressure pipe: 

PVC (DIN 8062), PE-HD (DIN 8074) and PP (DIN 8077). 

Notice!

 When the pressure pipe is connected to the pres-

sure outlet, do not seal the connection with hemp but wind 

not more than 6 layers of Teflon tape around the outlet.

Acoustically isolate the pressure pipe, connect it to the 
pressure outlet with a 1" female thread and route it to the 
nearest downpipe. 

Notice!

 Tighten the fitting carefully to avoid damaging the 

pressure outlet.

5. If the pressure pipe is laid horizontally, the hand-over point

to the downpipe must lie 25 cm higher than the Plancofix. 

In the highest point, the pressure pipe must be extended to 
avoid a suction lifter. 

Functional test

A functional test must be carried out before laying the screed. 
Motor noises on starting up are not a cause for concern as they 
are normal in synchronous motors.

Fill  water  in  from  above  through  the  floor  drain  and  get  the 
Plancofix  to  pump  out  several  times.

 The full water capacity 

must be pumped! 
Also check for leaks in the inlet and pressure pipe. Later 
changes can only be made with a considerable effort.

Laying the screed

NOTICE!

 The Plancofix must be weighted down to keep it in po

-

sition during application of the screed.

The entire area can now be filled with screed.

After the screed has set, the enclosed square seal is bonded to 
the integrated sealing strip. After the customer has attached a 

further thin­bed waterproofing system, the area can be tiled.

4

Summary of Contents for PLANCOFIX LINE

Page 1: ...EN Instruction Manual JUNG PUMPEN DE B 45155 32 1902 PLANCOFIX PLANCOFIXPLUS...

Page 2: ...ng this information can be dangerous General danger to people Warning of electrical voltage NOTICE Danger to equipment and operation Qualification and training of personnel All personnel involved with...

Page 3: ...ugging it from the mains or turning off the main switch or triggering the FI cir cuit breaker and ensure that the power supply to the unit can not be switched on again by anyone else NOTICE Never put...

Page 4: ...around the outlet Acoustically isolate the pressure pipe connect it to the pressure outlet with a 1 female thread and route it to the nearest downpipe Notice Tighten the fitting carefully to avoid dam...

Page 5: ...thout a drain Notice Do not seal the inner side of the gap that runs around the edge MAINTENANCE WARNING Before carrying out any work always disconnect the Plancofix from the power supply and ensure t...

Page 6: ...2008 EN 61000 3 2 2014 EN 61000 3 3 2013 DE Richtlinien Harmonisierte Normen CS Sm rnice Harmonizovan normy DA Direktiv Harmoniseret standard EN Directives Harmonised standards FI Direktiivi Yhdenmuk...

Page 7: ...Plancofix Plancofix plus 7...

Page 8: ...85 Abdeckung Cover JP45594 Abdeckung klein Cover small JP45595 Ablaufrost Grid JP45596 Deckel Motorraum Cover for motor JP45597 Schwimmer Float JP45598 Mikroschalter Micro switch JP45599 Schaltwelle S...

Page 9: ...l JP45595 Ablaufrost Grid JP45596 Schwimmer Float JP45598 Deckel Motorraum Cover for motor JP45597 Mikroschalter Micro switch JP45599 Schaltwelle Switch cam JP48072 Netzleitung Cable JP45603 Motorspan...

Page 10: ...arks of Pentair or its subsidiaries in the United States and or other countries 2019 Pentair Jung Pumpen Pump Technical Services Limited Pump House Unit 12 Bilton Road Industrial Estate Erith Kent DA8...

Reviews: