Note: If using installation clips, proceed to step 4N.

4

 

SETTING AND FASTENING THE DOOR (CONTINUED)

Interior

Exterior

Fixed Panel

Threshold

3G

3H

4L

4M

Frame Screw Method:

Installation Clip Method:

N. 

Fasten the door to the opening

 by driving two #8 x 1-1/4" corrosion resistant screws into 

the pre-punched holes in the clips. If the clips are bent and fastened to the interior stud/
block, install the screws as close to the bend as possible.

Note: DO NOT shim above the door. For masonry openings use two 3/16" x 1-1/2" 
masonry screws per clip. Pre-drill the masonry before attempting to drive the screws in.

O. 

Drive #10 x 3-1/2" corrosion resistant wood screws 

through the holes in the 

threshold in to the floor.

Note: For concrete floors, use masonry screws a minimum size of 3/16" x 3-1/2".

4N

L. 

Apply sealant and insert a #8 x 2-1/2" pan head (provided) or 3/16" x 1-3/4" 
concrete screw into each hole

 in the bottom of the door frame, as indicated above.

M. 

Position and secure the panel retainers

 by drilling pilot holes through the remaining 

holes in the retainer into the sill support or wood blocking, then apply sealant to the 
holes and insert a screw into each hole as specified below.

 

Aluminum sill support: 9/64" pilot holes, #10 x 3/4" thread cutting screws (provided).

 

Wood blocking:

 1/8" pilot holes, #10 x 2-1/2" flat head corrosion resistant wood 

screws (provided).

 

Masonry floor:

 3/16” x 1-3/4” concrete screws. Pilot drill per screw manufacturer’s 

recommendations.

Summary of Contents for 81CM0100

Page 1: ...d additional care Determining the appropriate installation method is the responsibility of you your architect or construction professional If you have questions please contact your local Pella retaile...

Page 2: ...asure Level Sealant gun Square Hammer Screwdriver Utility knife Wide jaw pliers Reciprocating saw 1 8 and 1 4 drill bit Drill 4 5 4 5 Installation will require two or more persons for safety reasons 1...

Page 3: ...ealant and other debris from the door opening 2B NOTE 2B 2B 2A F If the weep holes of the existing sill have been cut away drill new weep holes in the existing door jambs Be sure to drill weep holes i...

Page 4: ...ound the end of the pan Dry t the sill pan and the door into the opening J If there is a step down at the exterior of the door opening cut the sill nosing to the rough opening width plus two times the...

Page 5: ...2L M If using sill nosing with a step down Install the sill pan and sill nosing into the opening Press down to seal them into the opening DO NOT overlap N Apply sealant at nosing ends continuing from...

Page 6: ...B Remove the shipping spacers Carefully slide the movable panel halfway open and remove the spacers from both the top and bottom of the movable panel C Remove the venting panel by lifting it off of th...

Page 7: ...o the opening and that the door anges will overlap the stucco or existing aluminum door frame by a minimum of 1 2 on all sides REMOVE THE DOOR FROM THE OPENING D Place three 3 8 beads of sealant Place...

Page 8: ...Note If the dimensions are not equal check to make sure the ns are folded out to 90 at all points K Secure the frame Insert a 1 wide shim behind the pilot hole at the lock strike s Insert a 8 x 2 1 2...

Page 9: ...corrosion resistant wood screws through the holes in the threshold in to the oor Note For concrete oors use masonry screws a minimum size of 3 16 x 3 1 2 4N L Apply sealant and insert a 8 x 2 1 2 pan...

Page 10: ...he exterior of the building tilt the top of the panel toward the door frame and insert the top of the door panel into the top track Move the bottom of the panel toward the door frame until it is verti...

Page 11: ...ion of the foam and will minimize squeeze out Apply sealant across the interior surface of shims to create a continuous seal For doors with jamb extensions installed ensure the foam is placed between...

Page 12: ...urface Clad Exterior Frame The exterior frame is protected by aluminum cladding with our tough EnduraClad baked an factory nish that needs no painting Clean this surface with mild soap and water DO NO...

Page 13: ...ruction must anticipate some water in ltration it is important that the wall system be designed and constructed to properly manage moisture Pella Corporation is not responsible for claims or damages c...