4
B. Equipment storage and installation requirements.
The equipment should be stored or installed in a shady, normal
temperature, ventilated and dry place.
C. The equipment should be unload and transfer by forklift.
D. SPECIFICATIONS OF CONCRETE
(See Fig. 6)
Specifications of concrete must be adhered to the specification as following.
Failure to do so may result in lift and/or vehicle falling.
1. Concrete must be thickness
120
mm minimum and without reinforcing steel bars,
and must be completely dry before lift installation.
2. Concrete must be in good condition and must be of test strength 3,000psi
(210kg/cm²) minimum.
3. Floors must be level with no cracks or holes.
E. POWER SUPPLY
The electrical source must be 2.2kw minimum. The source cable size must be
2.5mm² and in good condition of contacting with floor.
Fig.6
Concrete intensive must be
3,000psi (210kg/cm²)
55
Fig.5
12
0m
m