background image

 

11 

ASSEMBLY INSTRUCTIONS INGROUND POST MODELS 

 

PH-45-IG-LP     (Liquid Propane), PH-50-IG-N     (Natural Gas)  
PH-45-IG-D-LP (Liquid Propane), PH-50-IG-D-N (Natural Gas)  
for permanent inground post mounting.  “D” indicates heater with direct light 
electronic ignition, no standing pilot.  (Requires switched 24 Volt power supply to 
heater.) 

 

   
 Step 1

 

 Determine a safe, level and stable location for the        

heater to be installed. 
Step 2 
Bury ground support pipe in ground so that 
approximately 6” is protruding above ground level.  
Ensure that support pipe is plum and securely 
supported in concrete. 
Step3

 

Remove the 3/8” x 1” bolt in the base of the heater 
head and set aside. (Figure 2  previous page 7). Secure 
heater head to flexible hose protruding from the top of 
the post.  Use two pipe wrenches to securely tighten.  
A suitably approved gas pipe sealant must be used for 
all gas connections.  Slide head assembly into post. 
Align the 3/8” hole in the post with the 3/8” threaded 
hole in the base of the heater head, and replace the 
3/8” x 1” bolt.  Secure tightly. 
Step 4 
Insert post into the ground support pipe and fasten 
with hardware provided.  Connect the gas supply to 
the nipple protruding from the lower side of the tube.  
The gas supply piping and electrical supply (if 
applicable) must be done in accordance with all local 
and applicable codes.  Only those licensed and 
qualified in the installation of gas-fired appliances 
should be engaged to install this appliance. 
Step 5 
Secure the reflector to the heater head with the             
hardware provided. 

 
D-Direct Lite:  If your heater has been supplied with a 24 Volt remote switching option, or 
direct light electronic ignition, connect your switched 24 V power supply to the spade 
connectors protruding from the bottom end of the post. Connect spade connectors at the top 
of the post to the marked connections on the heater head.  All supply wiring must be done in 
accordance will national, local and applicable codes.   Only those qualified and experienced 
in such wiring should be engaged for the installation of the electrical supply.

Gas  shutoff
by others

Underground
gas supply

Underground
pipe support

Ground level

Summary of Contents for PH series

Page 1: ...tentivement les instructions d installation de fonctionnement et d entretien avant de proc der l installation ou l entretien de cet quipement This manual applies to the following Patio Plus models PH...

Page 2: ...ustment alteration service or maintenance can cause injury property damage or death Read the complete installation manual and all warning labels on the appliance before installation or servicing this...

Page 3: ...maintained Combustible materials are considered to be wood compressed paper plant fibers or other materials capable of being ignited and burned Such materials shall be considered combustible even thou...

Page 4: ...atios must be large enough to meet the clearance to combustibles and ventilation requirements as provided for in all applicable codes For very small enclosed patios Patio Plus heaters may not be suita...

Page 5: ...tach regulator to your L P tank or gas line securely Leave the L P tank outside the cabinet for the testing procedure 3 Open the valve of the L P tank or turn main gas valve to heater ON then leave th...

Page 6: ...be used on L P gas special precautions should be observed when handling L P cylinders Remember that this is gas and under pressure which must be handled with care Ask your L P gas dealer to show you t...

Page 7: ...ulator assembly Always store L P cylinders in a well ventilated space If you intend to store the heater indoors disconnect the L P cylinder and store it outside Disconnected cylinders must have a thre...

Page 8: ...the 3 post The top of the post can be identified by the 3 8 hole being at the top end Line up the 3 8 hole in the post with the 3 8 hole in the base of the heater head and replace the previously remo...

Page 9: ...de the decorative cover onto the post from the bottom Place the post into the basemount T on the weighted base and slide the decorative cover down over the post retainer Connect gas supply to nipple p...

Page 10: ...y into post Align the 3 8 hole in the post with the 3 8 threaded hole in the base of the heater head and replace the 3 8 x 1 bolt Secure tightly Step 4 Slide the decorative cover onto the post from th...

Page 11: ...f the heater head and replace the 3 8 x 1 bolt Secure tightly Step 4 Insert post into the ground support pipe and fasten with hardware provided Connect the gas supply to the nipple protruding from the...

Page 12: ...sition Ensure that the heater is installed so that it hangs level to the ground and that stress cannot be created on the gas supply piping Step 3 Apply a suitably approved pipe sealant to the nipple p...

Page 13: ...b will be in an immovable position Wait 90 seconds and the thermocouple will cool and knob will be released to re light pilot To Light Main Burner except Direct Lite After pilot is lit wait 30 seconds...

Page 14: ...e has no pilot Defective thermopile Defective gas valve Dirty pilot Replace thermopile Replace gas valve Clean pilot Main Burner won t light No 24 Volt power to unit Low gas pressure Blockage in orifi...

Page 15: ...ds a 3 YEAR warranty from the date of purchase to the original purchaser of this product against manufacturing defects in material and workmanship If this product fails to operate because of a manufac...