PF9700 Automated Hinge Gate
5.
8.
45 mins
5.
Assuming that the gate has now been closeed onto the threaded bar and has been levelled
accordingly the duct can be pushed through the hole in the gate tower.
6.
Once the duct has been fed through the duct hole the second pour can be made. The picture shown
displays the pour nearly complete. You must allow for ducting to link one tower to the other as you
have to have a communication cable to allow the Master/Slave function. Also it goes without saying
that the supply power must also be fed through into the tower.
7. This picture simply shows the tower installed with a finished surface. At this point the finished layer
has zero structural benefit so it can be any finish of your choosing.
8. Now you can connect the communication cable for the Master/Slave function and photo-cells etc,
also the panels supply voltage. All this is detailed in the rest of this manual. Please note that the
product must be earthed. We recommend that the supply voltage comes from a 14 amp breaker MCB,
not RCD and is not a tempoarary supply (such as a generator) as the panel monitors the supply and
will treat this as “dirty power”