background image

 

 

 

1. Package Inside 

In parallel kit, you will find the following items in the package: 

 

1 PCS of parallel board   

 

1 PCS of parallel cable 

 

3 PCS OP relay board 

 

1 PCS of share current cable 

 

3 PCS of 2-pin red/black cables

3 PCS of 4-pin brown cables and 1 PCS of14-pin grey cable 

 

3 PCS of brown wires(each with a yellow& white core) and 1 PCS of blue wire   

 

Long screw and short screw for assembly 

 

CNTL board and COMMU board

optional

 

Note: 

The specs of relay board, wire, and cable are different for 10K, 10k (L), 20K , 20K (L) 30K, 30K(L) model. 

Please DO NOT mix them.   
The following picture is just for reference:   

 

 

2. Installation 

Warning: 

(For standard model) 

● Make sure the UPS is not turned on before installation. The UPS should not be turned on during installation. 

● Cut off all the power supply to the unit before installation. 

Warning:

 

(For long-run model) 

● Make sure a DC breaker or other protection device between UPS and external battery pack is installed. If not, 

please install it carefully. Switch off the battery breaker before installation. 

● Cut off all the power supply to the unit before installation. 

 

 

2.1 Uncover the UPS 

Uncover the UPS that intend to be paralleled by demounting all screws, and the following picture is used to 

show the PCBA boards location in the UPS:     

Parallel Kit Installation Guide For Galleon(pro) 3-3   

V. 4.0 

 

Summary of Contents for Galleon

Page 1: ...llowing picture is just for reference 2 Installation Warning For standard model Make sure the UPS is not turned on before installation The UPS should not be turned on during installation Cut off all t...

Page 2: ...ifferent between these two boards the part number The beginning 10 number of the series number and firmware label Label on the MCU in the picture just for reference different version UPS may have diff...

Page 3: ...control board demount the small PCBA board Demount the 3 white screws disconnect the 50 pin cable Replace the PFC control board with a new one It is better assemble the small PCBA first then assemble...

Page 4: ...unt the screw Then pull the INV control board Flipping over the INV control board you can see the glue on the connectors remove the glue then dis connect all the cables Replace the INV control board w...

Page 5: ...the cables on the communication board and demount the srews that used to fasten the communication board to the rear panel Replace the board with a new one connect the cables install the screws 2 3 Par...

Page 6: ...nect CN001 to CN15 of INV1 2 board Connect CN002 to CN16 of INV1 2 board Connect CN003 to CN15 of INV3 board Step 5 Connect the wires that demounted from the OP EMI board by step2 Connect R1 to P1 of...

Page 7: ...upply cable to CN9 of parallel board Connect the S phase current equalizer cable to CN10 of parallel board Connect the T phase current equalizer cable to CN11 of parallel board Step 8 Remove covers fo...

Page 8: ...rt red black cable to CN10 of communication board Step 11 Connect the S phase current equalizer cable the longer red black cable to CN20 of INV 1 2 board Step 12 Connect the T phase current equalizer...

Page 9: ...board Connect the 14 pin grey cable to CN11 of INV control board Step 14 Assemble the INV control board back to INV1 2 board and then make the 14 PIN grey cable through the middle iron board Step 15 C...

Page 10: ...Long Backup Unit 3 Wiring Connection for Parallel Operation Please follow the below steps to connect cables and wires for Gallon 3 3 parallel models Step 1 Parallel cable and share current cable conne...

Page 11: ...each UPS to an output breaker 4 Connect all output breakers to a major output breaker Then this major output breaker will directly connect to the loads Step 3 If the UPS is connected to external batt...

Page 12: ...onverter enable or disable f bypass enable or disable g bypass open or forbidden h frequency auto detect enable or disable i inverter short clear enable or disable 3 Turn on the UPS into the line mode...

Page 13: ...ve this setting into EEPROM Output A voltage calibration Interface Setting Parameter 2 it always shows OP V as output voltage Parameter 3 it shows the internal measurement value of the output A voltag...

Page 14: ...arallel system supplies power to the loads via the bypass c Check the LCD whether displays the parallel information as showed in the below picture If parallel UPS systems are successfully set up it wi...

Page 15: ...breaker only for long run model and output breaker of each UPS c Press the ON button of one UPS to set up the power supply UPS will enter to power on mode After initialization UPS will enter to No Out...

Page 16: ...stem All UPS will transfer to bypass mode c Remove all the maintenance bypass covers and set the maintenance switches from UPS to BPS d Turn off all the input breakers and battery breakers in parallel...