2. BitStorm 1900 Installation and Testing
2-58
BitStorm 1900 Installation and Maintenance Guide
1900-A2-GN20-00
Task 008: Installing Voice/Data & Filter Shelf
Connections
Use this procedure to connect the BitStorm 1900 to the EtherLoop
cross-connect in voice/data applications.
Requirements
This procedure requires the following tools and materials:
•
10 BitStorm 1900 cable harnesses
•
10 intermediate cables
•
10 BitStorm 1900 data cables
"Appendix B. Cabling Specifications," on page 115 contains the
specifications for the cables and wiring required in this procedure.
Step
Procedure
1.)
Place and secure the dedicated EtherLoop cross-connect on the
facility main distribution frame.
2.)
Designate and label one side of each block as "Line/CPE," and the
other side as "Voice."
3.)
Review pin and pair assignments in Figure 2-2, "Pin and Pair
Assignments for the Champ to Omni Grid Cable (Part #: 04-00007-
10)," on page 59.
Summary of Contents for BitStorm IP DSLAM 1900
Page 12: ...List of Tables viii BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...
Page 16: ...About This Document xii BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...
Page 48: ...1 BitStorm 1900 IP DSLAM 1 32 BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...