Digiplex DGP-NE96
- 49 -
Programming Guide
PCB Layout
Refer to the UL and ULC Warnings section of the Digiplex DGP-NE96 Reference &
Installation Manual for UL and ULC warnings.
PLEASE NOTE
: It is strongly recommended that you test
your system on a weekly basis, and have your system
checked by a qualified technician a minimum of every 3 years.
PLEASE NOTE:
When powering up the DGP-NE96 control panel (V1.02 or higher), the panel will begin a module
scan to verify if all the modules connected to the panel are operational. The scanning process will
take between 30 and 120 seconds to complete depending on the number of modules connected
to the control panel. The module scan is complete when the LCD keypad begins to show the
partition status. Only after the module scan is complete will the control panel be fully operational.
When installing the combus wires in a noisy environment, or
when connecting the combus across separate buildings, you
must use a shielded cable. Refer to