Install the Server
Related Information
■
“Rack Compatibility” on page 30
■
■
“Installing the Rackmount Kit” on page 33
■
“Determine Correct Rackmount Hardware” on page 35
Install the Server
Caution -
Do not attempt to move the server alone without a lift. For a one-person installation,
all the main CRUs must be removed, and a lift must be used. For a two-person installation, all
the CRUs must be removed, and a lift is optional.
1.
Prior to installing the server, confirm that you have removed the following
components.
■
Both processor modules
■
The main module
■
All four power supplies
■
All five fan modules
Refer to the
SPARC T8-4 Server Service Manual
for removal instructions.
2.
If you are using a mechanical lift, ensure that the lift is level and stable.
3.
Lift the server up to the correct height.
Ensure that the bottom edge of the server has cleared the bottom of the shelf rails.
Installing the Server
39
Summary of Contents for SPARC T8-4
Page 1: ...SPARC T8 4 Server Installation Guide Part No E80509 01 September 2017 ...
Page 2: ......
Page 8: ...8 SPARC T8 4 Server Installation Guide September 2017 ...
Page 10: ...10 SPARC T8 4 Server Installation Guide September 2017 ...
Page 22: ...22 SPARC T8 4 Server Installation Guide September 2017 ...
Page 28: ...28 SPARC T8 4 Server Installation Guide September 2017 ...
Page 64: ...64 SPARC T8 4 Server Installation Guide September 2017 ...
Page 82: ...82 SPARC T8 4 Server Installation Guide September 2017 ...
Page 88: ...88 SPARC T8 4 Server Installation Guide September 2017 ...