Install the Shelf Rails
■
“Installing the Rackmount Kit” on page 33
■
“Determine Correct Rackmount Hardware” on page 35
■
“Install the Shelf Rails” on page 37
Install the Shelf Rails
1.
Place the left shelf rail in the marked location.
Note -
The shelf rails are marked
FRONT LEFT
and
FRONT RIGHT
(as viewed from the front
of the server). An
up
arrow indicates proper orientation.
2.
Secure the rear shelf rail bracket at the top and bottom holes using two Torx T30
screws.
Installing the Server
37
Summary of Contents for SPARC T8-4
Page 1: ...SPARC T8 4 Server Installation Guide Part No E80509 01 September 2017 ...
Page 2: ......
Page 8: ...8 SPARC T8 4 Server Installation Guide September 2017 ...
Page 10: ...10 SPARC T8 4 Server Installation Guide September 2017 ...
Page 22: ...22 SPARC T8 4 Server Installation Guide September 2017 ...
Page 28: ...28 SPARC T8 4 Server Installation Guide September 2017 ...
Page 64: ...64 SPARC T8 4 Server Installation Guide September 2017 ...
Page 82: ...82 SPARC T8 4 Server Installation Guide September 2017 ...
Page 88: ...88 SPARC T8 4 Server Installation Guide September 2017 ...