Install the Storage Server Into the Slide-Rail Assemblies
3.
Insert the mounting brackets into the slide-rails, and then push the storage
server into the rack until the mounting brackets encounter the slide-rail stops
(approximately 12 inches, or 30 cm).
Callout
Description
1
Inserting mounting bracket
into slide-rail
2
Slide-rail release lever
4.
Simultaneously pull down and hold the slide-rail release levers on each
mounting bracket while you push the storage server into the rack. Continue
pushing the storage server into the rack until the slide-rail locks (on the front of
the mounting brackets) engage the slide-rail assemblies.
Installing the Storage Server Into a Rack
39
Summary of Contents for EXADATA X6-2
Page 2: ......
Page 8: ...8 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 14: ...14 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 24: ...24 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 60: ...60 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 66: ...66 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...
Page 70: ...70 Oracle Exadata Storage Server X6 2 Extreme Flash Installation Guide July 2018 ...