Verify Operation of Slide-Rails and Cable Management Arm
a.
Simultaneously pull and hold the two green release tabs (one on each side
of of the storage server) toward the front of the storage server while you
push the storage server into the rack. As you push the storage server into
the rack, verify that the CMA retracts without binding.
Note -
To pull the green release tab, place your finger in the center of the tab, not on the end,
and apply pressure as you pull the tab toward the front of the storage server.
b.
Continue pushing the storage server into the rack until the slide-rail locks
(on the front of the storage server) engage the slide-rail assemblies.
You will hear an audible click when the storage server is in the normal rack position.
6.
Adjust the cable straps and the CMA, as required.
Related Information
■
“Install the Storage Server Into the Slide-Rail Assemblies” on page 38
■
“Install the Cable Management Arm” on page 40
Installing the Storage Server Into a Rack
53
Summary of Contents for Exadata Storage Server X6-2 High Capacity
Page 2: ......
Page 8: ...8 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 24: ...24 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 64: ...64 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 68: ...68 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...