Install the Cable Management Arm
Note -
To pull the green release tabs, place your finger in the center of each tab, not on the end,
and apply pressure as you pull the tab toward the front of the storage server.
b.
Continue pushing the storage server into the rack until the slide-rail locks
(located on the front of the storage server) engage the slide-rail assemblies.
You will hear an audible click when the storage server is in the normal rack position.
15.
Connect cables to the storage server, as required.
Instructions for connecting the storage server cables are provided in
Note -
Power cables should already be installed in the Sun Rack II 1042 (1000-mm) system
rack.
16.
Open the CMA cable covers, route storage server cables through the CMA's
cable troughs, close the cable covers, and secure the cables with the six Velcro
straps.
50
Oracle Exadata Storage Server X6-2 High Capacity Installation Guide • July 2018
Summary of Contents for Exadata Storage Server X6-2 High Capacity
Page 2: ......
Page 8: ...8 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 24: ...24 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 64: ...64 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...
Page 68: ...68 Oracle Exadata Storage Server X6 2 High Capacity Installation Guide July 2018 ...