Caution 

 
The  moisture  condensation  formed  when  igniting  the  boiler  for  the  first  time  may  be  of  such  degree  that  the 
boiler  could  be  considered  leaking  erroneously.  This  condensation  will  disappear  as  soon  as  the  boiler 
temperature reaches 70 °C. 
 
Adjust  the  secondary  air  volume  so  that  no  smoke  appears  at  the  top  of  the  chimney  after  the  fuel  kindles 
properly. The secondary air volume, however, needs to be adjusted keeping the boiler output into consideration. 
Excessive secondary air causes supercooling in the heating chamber.  
 
When refueling open the charging door carefully to avoid burning injury, should the flame blast abruptly.  
 
Take care that the fuel level does not fall under the bottom edge of the underburning partition during operation. 
Should  this  happen,  it  is  necessary  to  add  wood  before  coal  to  avoid  fire  extinguishing.  Due  to  this,  the  boiler 
shall be refueled in a timely manner and charging shaft shall be kept full at all times. This will reduce choking of 
the boiler and increase the operating economy. 
 
Ash and cinder shall be removed from the grate as needed during operation. This is performed using the grate 
lever located on the side wall of the boiler. Short motions will make a small ash fall through, while long swings 
towards the front side of the boiler will remove also bigger cinder pieces. The lever shall always be returned to 
neutral position after the grate cleaning is completed. Check whether the ashtray compartment is filled with ash 
completely,  since  this  would  obstruct  supply  of  a  sufficient  air  volume  under  the  fire  bars.  If  this  check  is  not 
performed properly, the fire bars and grate mechanism may overheat and be damaged. 
 

Cleaning the boiler 

 
The  boiler  shall  be  cleaned  every  14  days  based  on  the  heating  method.  Cleaning  of  the  heat-exchanging 
surfaces is very important to maintain economical operation. Cleaning of this boiler is very easy, since the main 
heat-exchanging  surface  is  accessible  after  opening  the  cleaning  door.  Segments  shall  be  cleaned  using  the 
wire brush and persistent layer using scraper. Impurities fall through the rear section of segments onto the fire 
bridge. From there they move through the burning shaft into the ashtray compartment. This shaft can be cleaned 
through opening in the front wall, however, cleaning is required several times a season only. The secondary air 
supply pipe shall be cleaned occasionally after removing the lid of the secondary air on the side of the boiler in its 
bottom  section.  Cleaning shall be carried out using the steel brush designed for cleaning the segments. Clean 
the  flue  gas  side  also.  Impurities  will  fall  into  the  ashtray  compartment  when  the  secondary  air  supply  is  open 
fully.  We  recommend  to  knock  on  the  side  walls  of  the  ashtray  compartment  in  the  place  of the secondary air 
inlet with tools in order to release dust settled on the walls of segments.  
 
The boiler shall be cleaned thoroughly after the heating season and overall check shall be performed. This will 
extend its service life. Cleaning of boiler, and the heat-exchanging surfaces in particular, is very important for the 
operating economy. If the boiler is not cleaned properly the temperature of flue gases leaving to the chimney can 
increase by up to 100 °C, which represents a substantial energy loss. After each cleaning check removal of soot 
from the fire bridge under the segments (see Fig. 3, pos. 23).  

 
ATTENTION !!!

 Ash shall be put into incombustible container fitted with a cover. 

 

 

G)   Maintaining the boiler and heating equipment 

 
Prior to commissioning the heating unit it is necessary to prime the water system. Soft water should be used, if 
possible. The water shall be primed by the filling and discharging valve, which is located next to the return water 
coupling.  
 
The water shall not be taken from the boiler and heating equipment during operation. Check the water level in 
the  heating  equipment  occasionally.  Refill  if  needed.  To  protect  the  equipment  against  rust,  avoid  discharging 
water  from  the  heating  equipment  or  use  anticorrosive  agent  for  example  INHIKOR,  FRITERM 
(www.velvana.cz); follow manufacturer's instructions.  
 
Never allow the boiler to 

exceed 

90 °C. Fine bubbling when the exiting water exceeds 80 °C does not indicate a 

defect.  However,  bubbling  at  lower  temperatures  is  not  allowable.  This  indicates  incorrect  assembly  of  the 
heating system.  

Summary of Contents for H 635

Page 1: ...ting of supplied accessories 4 E Listing of replaceable spare parts 4 F Instructions for use 5 G Maintaining the boiler and heating equipment 6 H Safety instructions for installing and using the boile...

Page 2: ...y effect considerably g The large volume ashtray compartment allows a long term operation with no need of the frequent ash removal B Technical description The boiler the height of which is 1 606 mm fo...

Page 3: ...l Parameter Unit H 635 H 650 Operating flue mbar 0 25 0 3 Water volume l 80 110 Smoke flue diameter mm 160 160 Hydraulic loss of the boiler T 20 10 mbar 0 7 0 2 0 07 0 2 Boiler class 1 1 Burning time...

Page 4: ...7 Instruction manual E Listing of replaceable spare parts Component Pieces 1 Cleaning door 1 pc 2 Refueling door 1 pc 3 Ash tray door 1 pc 4 Firing flap 1 pc 5 Underburning through burning flap 1 pc 6...

Page 5: ...er ignition Add wood and other fuel as needed until the fuel level exceeds the lower edge of the underburning partition Then charge such quantity of fuel which will fill the charging shaft up to the l...

Page 6: ...r using scraper Impurities fall through the rear section of segments onto the fire bridge From there they move through the burning shaft into the ashtray compartment This shaft can be cleaned through...

Page 7: ...release Individual pipes of the smoke flue shall be slid into each other with at last 80 mm overlap We recommend that the distance from the boiler to the chimney be less or equal to 1 m The smoke flu...

Page 8: ...appliance shall be used in compliance with instructions provided in this manual The boiler may be left unattended provided that the output is set to a level when overheating of the system cannot occur...

Page 9: ...Each heating system shall be fitted with at least one safety valve positioned on the discharge pipe or on the boiler and the pressure gauge Location installation and inside diameter of the safety valv...

Page 10: ...fference determined for steel boilers at 50 kPa P1 Absolute value of the hydrostatic pressure kPa V Increased volume of water in the whole system dm 3 V G v Where G Weight of water in the heating syst...

Page 11: ...rheating is avoided As soon as water in the boiler cools down the valve starts closing automatically and the cold water supply to the safety exchanger is closed completely after all This activity may...

Page 12: ...Hot Water Boiler Manual Models H 635 H 650 12 Boiler connection Reservoir for TS 130 Cooling water discharge valve sensor Honeywell TS 130 valve from the cooler...

Page 13: ...n 4 Firing flap 5 Underburning through burning flap 6 Long fire bar 7 Short fire bar 8 Grate mechanism 9 Long fire bar support 10 Short fire bar support 11 Fire clay panel 12 Ash tray 17 Burner hole p...

Page 14: ...4 View of the boiler 1 Cleaning door 2 Refueling door 3 Ashtray door 13 Firing flap lever 14 Grate control lever 15 Secondary air lever 16 Firing flap 19 Pressure gauge 20 Filling and discharge valve...

Page 15: ...on Primary air inlet Primary air Fig 5 Boiler section during firing 1 Open the firing flap 2 The underburning through burning flap can also be set to through burning 3 Set the flap to underburning bef...

Page 16: ...ion fuel underburning The underburning method is used for the following fuel types Lignite Anthracite Small wooden waste Close the firing flap immediately after a proper burning is obtained and set an...

Page 17: ...sh as household refuse Metal parts are to be given over in a junk storage place After termination of the product operating life cover and grates shall be liquidated as metal waste insulation material...

Page 18: ...Phone 420 571 675 589 Fax 420 571 611 225 Shipping date EXW _____________________ Warranty conditions This warranty certificate provides a proof of quality and completeness The manufacturer confirms t...

Page 19: ...for 60 months from the EXW shipping date This guarantee is subject to the fact that the pressure expansion vessel has not been used in the heating system and leakage was caused by the inferior quality...

Page 20: ...is impossible to proceed as per point a the manufacturer is entitled to specify the method date and performance of the repair by its service personnel or contractual partner c The user shall allow the...

Page 21: ...en v hody je pot ebn vyplnit registra n kartu a zaslat ji na na i adresu OPOP spol s r o Obchodn odd len Za ovsk 750 757 01 Vala sk Mezi Po obdr en vypln n ho formul e V m obratem za leme Z kaznickou...

Page 22: ...441 T 58 5341826 603 993849 LITOVEL 22 Ku m n Josef M n k 3 B la Lhota T 58 5340503 737 583317 LITOVEL 23 Svoboda Ji Havl kov 996 T 326 323779 604 942834 MLAD BOLESLAV 24 Mixed Velebudice Stavba 39 T...

Reviews: