Pagina 5 di 45
cod.ITRIP250092D
PRELIMINARY
TRIPARK 25
5
4. Safety
Before starting installation, make certain that all necessary P.P.E.
(personal protection equipment) is available. We recommend using the
P.P.E. required by current law.
4.1.
Safety signage
Below is an indication of the yard standard safety signage
WORK GLOVES
Must always be worn while in the
yard.
SAFETY SHOES
Must always be worn while in the
yard.
SAFETY HARNESS
Must always be worn when
working inside the shaft and on
scaffolding higher than 2 m.
HELMET WITH CHIN
STRAP
Must always be worn while in the
yard.
EAR PROTECTION
Must always be worn while using
noisy equipment.
SAFETY
GOGGLES/GLASSES
Must always be worn while in the
yard.
5. Preparation of the yard
5.1.
Work to be performed before starting
installation
Before starting installation, perform the following operations:
1 Check that the safety guards are properly installed on all doors at all
floors, as indicated in the drawing below, and that the pertinent danger
signs have been posted.
2 Check availability of an electrical power supply line with ground and
protected upstream by a magnetothermal differential switch set to cut in
at 30mA in compliance with CEI 64/8
Apply net or other form of
protection at all doors to prevent
objects from falling.