You can find BR1 - Square
Drive Bit for the screws in
with the Hardware Kit Bag.
1. Floor Section
Flush with framing
top/bottom.
Plywood Floor - 2pcs.
(Part 1D)
Floor Frames - 2pcs.
(Part 1A)
Concrete Pad
(optional foundation method)
Exploded view of all parts necessary to complete
Floor Section. Identify all parts prior to starting.
Note: Floor Footprint is 141 1/2” wide x 45 1/2” deep.
2.
Lay out both complete floor joist frames as illustrated. The footprint for the
floor when attached together will be 141 1/2” wide x 45 1/2” deep. Attach
frames together with
6 - 2 1/2” Screws.
Hardware
S1
- 2 1/2” Screws
x 16 total
1.
Lay out
1A - Floor Frame
and two
1B - Floor Joists
as illustrated
above. Position the center of each Joist 15” from the outer edge of Floor
Frame. When correctly positioned, attach each Joist with
4 - 2 1/2” Screws
(2 per end).
You can find the Square Drive Screw
Bit in the Hardware Kit Bag.
Complete remaining Floor Frame the
same.
Parts
1A - Floor Joist Frames
(45 1/2” x 70 3/4”)
x 2
1B - Floor Joists
(1 1/2” x 3 1/2” x 67 3/4”)
x 4
Center Floor
Joists - 4pcs.
(Part 1B)
Hardware
S1
- 2 1/2” Screws
x 6 total
141 1/2”
45 1/2”
15”
15”
Floor Runners Short -
2pcs. (Part 1C)
Floor Runners Long -
5pcs. (Part 1CC)
Toll Free 1-888-658-1658 www.outdoorlivingtoday.com [email protected]