background image

14.

 

Position 

2D

 

- Door Header - Short

 on top 

of wall stud so it is flush on the outside with the 
wall siding. Attach by screwing down into top wall 
framing with 

3 - 3” Screws

.

Parts (Step 14 - 15)

 

2D - Door Headers - Short 

(2” x 3 1/2” x 26 1/4”) 

x 2

 

2E

 

- Door Header - Long

 

(2” x 3 1/2” x 84”) 

x 1

 

Hardware (Step 14 - 15) 

S4

 

- 3” Screws

  

x 10 total 

S2

 

- 1 1/4” Screws

  

x 4 total

Step to front  
and top.

Align flush 
outside with 
wall siding.

15.

 

Attach 

2D

 

- Door Header - Short

 to other side. Position and attach 

2E

 

- Door Header - Long 

between short door headers. The Long Door Header has an aluminum strip attached to the back for added 
support. Attach by screwing down into wall framing with 

2 - 3” Screws 

per side. Fasten aluminum strip to 

short headers with 

2 - 1 1/4” Screws

 per side.

Aluminum strip on back 
of Long Door Header

Door Header 
overhangs 
inside wall 
framing by 1/2”

  Toll Free 1-888-658-1658              www.outdoorlivingtoday.com        [email protected]

Page 13

Summary of Contents for SpaceSaver SS124-SLIDER-PLY-AK

Page 1: ...ding Doors Please take the time to identify all the parts prior to assembly Safety Points and Other Considerations Our products are built for use based on proper installation on level ground and norma...

Page 2: ...on the type of foundation you will be using Concrete slab or 4 6 inches of crushed gravel with paver stones or 4x4 stringers You can nd the footprint for your shed on Page 3 of your Assembly Manual I...

Page 3: ...of floor frame Saves money on materials easy to level and work with Gravel with Patio Paver Stones Excavate at least 6 deep and 6 wider than floor frame on each side 1 2 Cubic Yards of gravel required...

Page 4: ...Right 3E 1 x 3 x 45 Rear Soffit Center Roofs 3F 2 5 8 x 48 x 50 Outside Large Roof Plywood Panels 3G 1 5 8 x 48 x 45 1 2 Center Large Roof Plywood Panel 3H 2 5 8 x 50 x 5 3 4 Outside Small Roof Plywoo...

Page 5: ...e of Lap Siding Use if front wall panel siding is damaged Steps 53 55 48 52 S1 2 1 2 Screws S4 3 Screws Y2 90 Metal Bracket Roof x 4 x 234 x 44 x 190 x 305 S2 1 1 4 Screws N1 1 1 2 Finishing Nails BR1...

Page 6: ...ails Brush off dirt from walls Brush off snow from roof regularly Routinely remove needles and leaves from roof Painting Staining Your cedar shed if left untreated will weather to a silvery grey colou...

Page 7: ...mes together with 6 2 1 2 Screws Hardware S1 2 1 2 Screws x 16 total 1 Lay out 1A Floor Frame and two 1B Floor Joists as illustrated above Position the center of each Joist 15 from the outer edge of F...

Page 8: ...aution Be careful when laying floor down not to bend or twist floor Note Having a level foundation is critical Choosing a foundation will vary between regions Typical foundations can be concrete pads...

Page 9: ...f all parts necessary to complete the Wall Section Identify all parts prior to starting Angled Wall Extenders 2pcs Part 2G Side Rear Wall Panels 5pcs Part 2A Bottom Wall Plates 5pcs Part 2B Front Wall...

Page 10: ...e if panel is facing up or down Recently attached Bottom Plate is on bottom of panel Outside 2x3 framing of wall panel should be positioned flush with the outside of floor framing when properly aligne...

Page 11: ...joists Wall siding should overhang floor by approximately 3 4 When positioned correctly attach both side wall panel studs together as per Step 10 10 Position rear solid wall into place on plywood floo...

Page 12: ...Place Front Walls so wall framing is flush with floor frame and siding overhangs Attach with 3 2 1 2 Screws per panel as per Steps 10 12 12 Complete remaining side wall attachment as per Steps 10 11...

Page 13: ...d top Align flush outside with wall siding 15 Attach 2D Door Header Short to other side Position and attach 2E Door Header Long between short door headers The Long Door Header has an aluminum strip at...

Page 14: ...de wall Parts 2G Angle Wall Extenders L R 2G 45 1 2 wide x 2 2F Top Triangular Siding Piece 2F Left Right x 2 Hardware N1 1 1 2 Finishing Nails x 6 total 17 Align wall framing of Angled Wall Extender...

Page 15: ...t protects overhanging siding on upper walls from damage Please remove before installing Overhanging siding Protective cleat 19 Complete opposite Angled Wall Extender positioning and attachment as per...

Page 16: ...shown above Align with top framing of front walls Attach with 4 2 1 2 Screws To complete Wall Section attach bottom 2x3 wall plates to plywood floor with 2 2 1 2 Screws per wall section Prior to secu...

Page 17: ...art 3E Front Soffits L R 2pcs Part 3B Front Soffit Center 1pcs Part 3C 142 1 4 142 1 4 Advice Prior to installing rafters take time to confirm your walls are level square and plumb Measure diagonal at...

Page 18: ...ront Rear 141 1 2 Parts 3A Rafters 1 1 2 x 2 1 2 x 54 x 9 3B Front Soffits Sides 1 x 3 1 2 x 48 x 2 3C Front Soffit Center 1 x 3 1 2 x 45 1 2 x 1 3D Rear Soffits Sides 1 2 x 3 1 2 x 48 x 2 3E Rear Sof...

Page 19: ...will sit approximately 1 8 away from wall siding This can vary slightly 25 Carefully flip completed Rafter Section over so Front Soffit is facing the front and place on SpaceSaver walls Note Double ch...

Page 20: ...are S4 3 Screws x 14 total 30 There are 4 different plywood roof panel sizes required to complete Start with an Outside Large Plywood Panel first Position so Plywood overhangs outside rafter by 2 In t...

Page 21: ...lywood Panels Position so plywood overhangs outside rafter by 2 In the front plywood will be recessed 1 8 back from rafter end With panels positioned correctly attach to rafters with 9 1 1 4 Screws fo...

Page 22: ...ront Corner Trim Part 4N Front Corner Filler Trim Part 4C Sliding Doors Part 4F Window Inserts Part 4V Front Corner Trim Part 4M Side Facia Part 4Q Side Rear Corner Trim Part 4P Rear Corner Trim Part...

Page 23: ...5 36 N1 1 1 2 Finishing Nails x 20 total Rear Skirting Gap Side Skirting 36 Gaps on outside will be covered by Corner Trim later Complete side and rear skirting attachments 37 Attach 4B Front Bottom S...

Page 24: ...red 38 Position and attach 4C Front Corner Filler Trim with 4 1 1 2 Finishing Nails per piece Filler trims won t be visible because they serve as nailing strips for the Corner Trims which will be atta...

Page 25: ...s 4E Aluminum Door Track x 2 Hardware S2 1 1 4 Screws x 16 total 3 8 Gap between Track and Door Header Extra piece of lap siding can be used as a spacer 3 8 Door Header Front Soffit Tracks meet in the...

Page 26: ...s meet in the middle Left Side Door Parts 4F Sliding Doors 36 x 73 x 2 Right Side Door Twist Roller Cart onto bolt After doors are hung you may need to adjust this until doors hang straight up and dow...

Page 27: ...of bottom skirting Door Tracks rest on Long Floor Runners Bottom of Door Stops and Door Tracks should be flush with each other Secure Door Tracks to shed with 6 3 screws per piece Secure Door Stops w...

Page 28: ...doors can not slide out of the track Secure each piece of Track Cover with 4 2 1 2 Screws Parts 4I Lower Door Track Cover 3 4 x 3 1 2 x 44 1 4 x 3 Hardware S1 2 1 2 Screws x 12 total Door Stop and Tr...

Page 29: ...door frame and attach with 5 1 1 4 Screws Parts 4G Interior Door Flange 3 4 x 3 1 2 x 71 1 2 x 1 Hardware S2 1 1 4 Screws x 5 total Left Side Door Left Side Door Right Side Door Door Flange attaches...

Page 30: ...g Nails aligning at bottom with wide trim Parts 4M Front Corner Trims 1 2 x 5 1 2 x 78 1 2 x 2 4N Side Front Corner Trims 1 2 x 2 1 2 x 80 x 2 Hardware N1 1 1 2 Finishing Nails x 32 total 5 1 2 tight...

Page 31: ...fter ends and Side Facia goes against Facia Nailing Strip Align so the Front Facia caps the Side Facia Attach Front Facia with 2 1 1 2 Finishing Nails per rafter end Attach Side Facia to the Facia Nai...

Page 32: ...s per rafter end 51 Attach 4R 4S Rear Facia onto rafter ends as per Steps 48 50 Small gaps may occur between the Center and Left Right Facia these will be covered by Facia Detail Plates in Step 52 Rea...

Page 33: ...ing in behind window Position window in cavity and secure with 8 1 1 4 Screws Caulk gap between siding and window at top This requires a large amount of caulking but is important to fill Later Window...

Page 34: ...arts 4W Window Trim Kit x 2 Top pc 24 1 16 x 1 Angle Ends Side Bottom pcs 23 x 3 Hardware N1 1 1 2 Finishing Nails x 32 total 55 Attach Y3 Door Handles and Y11 Black Hasp Handles and Hasp are position...

Page 35: ...Customer Service 2 On Time Shipping 3 Motor Freight Delivery 4 Quality of Materials 5 Assembly Manual 6 Overall Satisfaction Toll Line 1 888 658 1658 Fax 1 604 462 5333 sales outdoorlivingtoday com Th...

Reviews: