• FOR INSTALLATION ON NON-COMBUSTIBLE FLOORS 

ONLY - The boiler must not be installed on carpeting 

or vinyl 

fl

 ooring. Minimum clearances to combustible 

construction are:

Table 4   Clearance To Combustibles

TOP

24 IN.

FRONT

24 IN.

FLUE CONNECTOR

9 IN.

REAR

6 IN.

LEFT SIDE

6 IN.

RIGHT SIDE

24 IN.

 

NOTE:

 Clearance for access should exceed fire protection 

clearance.

• Install boiler in accordance with requirements of 

authority having jurisdiction, or in the absence of such 

requirements, CSA B139: Installation Code for Oil 

Burning Equipment.

• Where required by authority having jurisdiction, 

installation shall conform to Standard for Controls and 

Safety Devices for Automatically Fired Boilers, ANSI/

ASME CSD-1.

• Locate boiler in front of 

fi

 nal position before removing 

crate. Provide solid level base as near chimney as 

possible and centrally located with respect to the heat 

distribution system as practical. 

• Allow 24 inches in front, top and right hand side for 

servicing and cleaning or removing tankless water 

heating coil.

• When installed in utility room, door should be wide 

enough to allow largest boiler part to enter, or to permit 

replacement of another appliance such as water heater.

• Boiler shall be installed such that the oil ignition system 

components are protected from water (dripping, 

spraying, rain etc.) during appliance operation and 

service.

INSTALLATION PROCEDURE

• Remove crate and plastic protective wrapper, inspect for 

damage. 

• Move boiler to permanent position by sliding or walking.

WARNING

Improper installation, adjustment, alteration, service 

or maintenance could result in death or serious 

injury

.

!

   

WARNING

Fire hazard. Do not install boiler on combustible 

fl

 ooring or carpeting. Failure to follow these 

instructions could result in death or serious injury.

!

   

Summary of Contents for OBC II Series

Page 1: ...T IRON BOILER INSTALLATION OPERATION MAINTENANCE MANUAL Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com P N 240009512 Rev A 04 2012 Models OBC3...

Page 2: ...nts may result in personal injury or loss of life TO THE OWNER Installation and service of this boiler must be performed by a qualified installer TO THE INSTALLER Leave all instructions with boiler fo...

Page 3: ...a to be heated select boiler on basis of its Heating Capacity 5 Nozzle listed for use with Beckett Burner 6 Electrical service to be 120 Volts 15 Amps 60 Hz STANDARD EQUIPMENT Crated Boiler Flush Jack...

Page 4: ...l base as near chimney as possible and centrally located with respect to the heat distribution system as practical Allow 24 inches in front top and right hand side for servicing and cleaning or removi...

Page 5: ...sectional area of the openings to which they are connected Table 5 COMBUSTION AIR REQUIREMENTS Minimum Opening Requirement BTU Hr Input Mbh Unconfined Area Confined Area Outside Inside Outside Combust...

Page 6: ...d each opening shall have a minimum free area 1 square inch per 2 000 BTU per hour total input rating of all appliances in the enclosed space See Figure 5 D When ducts are used they shall be of the sa...

Page 7: ...ng as suggested in Figure 6 When boiler is used in connection with refrigerated systems A Chilled medium MUST BE IN PARALLEL with boiler Figure 6 Boiler Used In Connection With Refrigerated System B U...

Page 8: ...t the system or condition of the installation Although this method of piping is not typically required for baseboard heating systems A This method is used to protect systems using radiant panels and t...

Page 9: ...9 CONNECTING SUPPLY AND RETURN PIPING Figure 9 Bypass Piping Option Used to Protect From Converted Systems With High Water Temperature Figure 10 Typical Installation With Circulators...

Page 10: ...10 CONNECTING SUPPLY AND RETURN PIPING Figure 11 Typical Installation With Valves Figure 12 Typical Installation With DHW...

Page 11: ...fety relief valve outlet and downstream of union if used Terminate pipe with plain end not threaded Refer to local codes and appropriate ASME Boiler and Pressure Vessel Code for additional installatio...

Page 12: ...chimney performance Chimney should extend at least 2 ft above any portion of building within 10 ft See Figure 15 It should produce a 06 to 08 inch W C draft as measured with draft gauge between boiler...

Page 13: ...13 VENTING SYSTEM INSPECTION INSTALLATION P N 240005186 Rev 1 0 06 05 Figure 16 Final Placement Of Boiler With New Vent Safety Switch Installed...

Page 14: ...ended E Compression fittings on suction line often allows air to be drawn into fuel pump making it difficult to maintain oil pressure at the nozzle F Do not run overhead fuel lines from tank to oil bu...

Page 15: ...be installed on an inside wall about four feet above the floor 2 NEVER install a thermostat on an outside wall 3 Do not install a thermostat where it will be affected by drafts hot or cold pipes sunli...

Page 16: ...16 WIRING DIAGRAMS Figure 19 Wiring Diagram...

Page 17: ...ration Thermostat calls for heat Circulator turns on Limit checks boiler water temperature Burner ignition delayed until limit determines call for heat cannot be met by residual heat in boiler and hea...

Page 18: ...h limit point Burner should start B Verify Primary Control and Flame Sensor Flame Failure simulate by shutting off oil supply with hand valve while burner is on Sixty seconds after flameout safety swi...

Page 19: ...14 5 Disconnect oil line from burner Recommend replacing nozzle at start of each heating season Lubricate burner motor and circulator motor if required with few drops of good grade of light motor oil...

Page 20: ...ECR International 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...