Page | 25
5.2 HI-CAP N STONER OPREATION PROCEDURE
1.
Set the eccentric speed and tilt to
approximately
3/4
of
their
maximum setting. Set VFD air sped
to 15% for small material and about
30% for material larger than 1/8".
Open the feed gate slightly and
adjust the eccentric speed so that the
material spreads uphill slightly
faster than downhill.
2.
When 1/3 of the deck is covered, begin opening the air gate controls. As the
deck continues to fill, open the air gates only enough to maintain a
minimum fluidization.
3.
On many products a zone of light
material will form at the lower edge of
the bed as the deck fills. This is normal
and indicates that sufficient air is
present. If the percentage of heavy
material is high, you may note the
beginnings of a heavy separation in the
heavy discharge area.
FIGURE 11
FIGURE 12
Summary of Contents for Hi-Cap N Series
Page 6: ...Page 6 ...
Page 34: ...Page 34 this section intentionally left blank ...
Page 35: ...Page 35 V Appendices Appendix A Maintenance and Basic Troubleshooting ...
Page 41: ...Page 41 Appendix B The ABB ACS380 VFD ...
Page 43: ...43 P a g e Figure 17 VFD keypad display ...
Page 44: ...44 P a g e Figure 18 VFD keypad status line ...
Page 47: ...47 P a g e A 2 Programming the VFD from the Keypad Figure 20 Changing VFD parameters ...
Page 49: ...49 P a g e ...
Page 50: ...50 P a g e Appendix C Timer manual ...
Page 51: ...51 P a g e C 1 Getting to know timer operation ...
Page 52: ...52 P a g e C 2 Timer dip switch selection ...
Page 53: ...53 P a g e Appendix D Electrical and Dimensional drawings ...
Page 54: ...Page 54 D 1 Electrical drawings ...
Page 55: ...55 P a g e ...
Page 56: ...56 P a g e ...
Page 57: ...57 P a g e D 2 DIMENSIONAL LAYOUT DRAWINGS ...
Page 58: ......