10
Line routing
Mounting the connection flange on the outer tank
For the line routing, the foil and the wood must be drilled through in the area of the
discharge motor on the left or right side of a longitudinal board.
Depending on the conditions on site, the placement of the line routing may vary.
NOTICE
Drill carefully so that the foil does not tear.
Hole saw approx.
Ø
51 mm
±
1 mm for nozzles suction hoses
Hole saw approx.
Ø
30 mm
±
1 mm for cable entry
1. Drill through wood and foil.
2. Fasten the suction socket set
with 8 screws.
3. Mount and fasten pellet hoses
inside the tank.
50 mm
30 mm
50 mm
30 mm
No. 24 (1x)
10 Line routing