Nuaire Group BPC MRXBOX95-WM1 Installation And Maintenance Manual Download Page 10

Standard Assessment Procedure 2005 – Appendix Q MVHR Installation Guide 

Page 2 of 6 

Introduction 

This document is to be used in support of the SAP Appendix Q scheme which provides 
tested performance values for MVHR products. 

Note that all checklist items must be answered YES in order for the SAP Appendix Q 
test figures to be used in ‘As built’ SAP calculations.  If any checklist items are answered 
NO then SAP default figures must be used.  Systems must be designed by a 
manufacturer designer and sized correctly to qualify for SAP Appendix Q figures. 

SECTION 1: 

INSTALLATION GUIDANCE 

1. Ductwork Installation

Decision 

Yes, No or 

N/A 

Have the ducts been installed with as little air resistance and 
leakages as possible (flexible ducts should be avoided)?  

Note:  Refer to HVCA DW/143 document ‘A Practical Guide to Ductwork Leakage 
Testing’ for detailed guidance on air tightness.  Rigid plastic ducting is 
recommended and flexible duct should only be used in very short lengths and 
mainly just to connect the ductwork to the units/diffusers or to overcome particular 
obstructions. 

If flexible ducting has been used, has it been pulled taut to minimise 
system resistance? 

Has the number of duct bends been minimised to ensure adequate 
air flow and least resistance?  Bends should have a minimum radius 
at least the same as the diameter of the ducting used? 

Refer to Figure 1 if using flexible ducting 

Have the fans and ducting placed in unheated voids been insulated 
to reduce the possibility of condensation forming (see notes below)? 

Note:  Ducts should be insulated with the equivalent of at least 25mm of insulating 
material with a thermal conductivity of 0.04W/mK.  Where a duct rises vertically it 
may be necessary to fit a condensation trap in order to prevent backflow of any 
moisture in the product.  Insulation should be applied to both warm and cold air 
ducts.  Cold air ducts should be wrapped additionally with a vapour barrier outside 
the insulation.  Ducts with cold air running in warm environments will condense on 
the outside of the duct. 

Have recommended duct jointing collars and components been 
used to ensure appropriate duct performance (duct runs should be 
as air tight as possible)?   

Note:  All the joints should be sealed correctly either using duct tape or silicon.  

Summary of Contents for BPC MRXBOX95-WM1

Page 1: ... the pre drilled holes in the bracket and install with screws by others ensuring the interlock side is at the top fig 3 Figure 3 Fixing the mounting bracket to the wall 2 Install the unit on the wall by ensuring the bracket fixed to the rear of the unit interlocks over the wall mounted bracket fig 4 Figure 4 Mounting the unit on the wall mounted bracket Note Care must be taken to ensure the unit i...

Page 2: ...Figure 5 Typical example of a cupboard mounted unit Standard unit fixed to a block work wall Option 2 Wall Mounting If it is not practical to use a solid wall the MVHR unit should be fixed to a stud partition with a 25mm minimum thickness MDF panel solidly fixed behind the plasterboard If fixing to a stud wall the MDF panel should extend width wise over a minimum of 3 vertical studs with centres o...

Page 3: ...pt to a minimum A minimum distance of 300mm between the appliance and any bends in ductwork is recommended Ideally 150mm diameter or 204 x 60mm rectangular ducting should be used Refer to dwelling design drawing figure 9a and 9b on page 5 for further information Ducting joints must be sealed with silicone type sealant and shall be adequately and reliably fixed to the appliance 2 6 Ventilation flow...

Page 4: ...ly as an alternative the purge ventilation provisions given in ADF 2010 can be used where security is not an issue In this case minimum high extract rate for the sanitary accommodation should be omitted from the step 2 calculation Step 3 The required airflow rates are as follows n the maximum whole dwelling extract ventilation rate e g boost should be at least the greater of step 1 and step 2 Note...

Page 5: ...upply duct Air supply to lounge via Air Valve in ceilings Extract air from kitchen bathroom via Air Valve in ceilings Air supply to bedrooms via Air Valve in ceilings Top of ceiling void Top of ceiling void Nuaire wall mounted unit Air supply to bedrooms via Air Valve in ceilings Nuaire wall mounted unit MVHR DRAIN Condensate drain uninsulated drain pipe with min 5o fall running to SVP MVHR DRAIN ...

Page 6: ...ure 10 The IDC plug in connectors are provided for the connection of compatible sensors NOTE Do not run the data cable in the same conduit as the mains cable and leave a 50mm separation with any power cables Fuse 2A MAINS 230V 50Hz Room light Light switch Double Pole N L Fuse 2A MAINS 230V 50Hz Room lights Light switches Double Pole N L 3 Pole isolator 3 Pole isolator Kitchen switch Kitchen switch...

Page 7: ...ngportal gov uk building regulations approved documents partf associated A calibrated moving vane anemometer and hood will be required to carry out commissioning 5 Adjustment valves should be locked in place to prevent further adjustment 6 Once commissioned the home owner tenant should be informed that the unit should not be adjusted as it will have a detrimental effect on the indoor air quality a...

Page 8: ...ectrically competent person When ordering spare parts please quote the serial number of the unit and the ARC number of the purchase if possible This information will be available on the fan label 11 0 Warranty The 5 year warranty starts from the day of delivery and includes parts and labour for the first year and parts only for the remaining 4 years This warranty is conditional on planned maintena...

Page 9: ...lings assessed under The Building Regulations 2010 specifically SAP 2009 and Approved Documents L and F Completion of this document is therefore only required for dwellings assessed by SAP 2005 Customer Details Customer Name Address Telephone Number Date of Installation Name of Lead Contractor Design Project Number It should be noted that this guidance is not intended to replace product manufactur...

Page 10: ...or to overcome particular obstructions If flexible ducting has been used has it been pulled taut to minimise system resistance Has the number of duct bends been minimised to ensure adequate air flow and least resistance Bends should have a minimum radius at least the same as the diameter of the ducting used Refer to Figure 1 if using flexible ducting Have the fans and ducting placed in unheated vo...

Page 11: ...ry unit been fixed to a stable element of the building fabric e g wall or floor using manufacturer recommended supplied fixing brackets Has the condensation drain been fitted and the pipe insulated Have approved acoustic anti vibration mountings been used Note Special attention is needed to avoid transmission and stress to duct joints Has the unit been installed in a position that will permit acce...

Page 12: ... or N A Has the rating label been verified to establish suitability for the installation strategy and whether an earth is required e g voltage class I or II product status Has a local isolator been provided to enable the unit to be isolated for maintenance purposes Has the unit been fused in accordance with its power rating SECTION 2 COMMISSIONING GUIDANCE ...

Page 13: ...ution grilles been locked where possible to minimise unapproved occupant adjustment Figure 3 Ensure all external and internal windows and doors are closed Set fan speed using manufacturer data table Set normal daytime air flow on extract points starting at location furthest from unit Set normal daytime air flow on input points starting at location furthest from unit Step 1 Step 2 Step 3 Step 4 Ste...

Page 14: ...he customer been advised that opening windows is not recommended during normal use in order to ensure the energy efficient operation and performance of the balanced system Has the customer been advised not to seal natural air flows from room to room e g avoid door seals and thick pile carpets Has the customer been advised not to alter settings post commissioning Has the customer been advised to cl...

Reviews: