30
Chapter 2 Calculating transmission distance
212257-B
Table 3
shows typical loss values that can be used to calculate the transmission
distance for the point-to-point network in
Figure 11
.
Table 4
shows calculations used to determine maximum transmission distance for
the point-to-point network example in
Figure 11
.
Transmission distance calculation for the point-to-point network example in
Figure 11
:
•
•
•
Mesh ring transmission distance
The transmission distance calculation for the mesh ring configuration in
Figure 12
is similar to that of the point-to-point configuration with some additional loss
generated in the passthrough of intermediate CWDM OADM nodes.
Table 3 Point-to-point signal loss values
Signal loss element
value (dB)
Loss budget
30 dB
CWDM OMUX-8 mux loss
3.5 dB
CWDM OMUX-8 demux loss
4.5 dB
System margin
3 dB
Fiber attenuation
.25 dB per km
Table 4 Point-to-point maximum transmission distance calculations
Result
Calculation
Passive loss
Implied fiber loss
Maximum transmission distance
mux loss
demux loss
+
loss budget
passive loss
system margin
–
–
implied fiber loss
attenuation per kilometer
÷
3.5 dB
4.5 dB
8.0 dB Passive Loss
=
+
30 dB 8 dB
–
3 dB
–
19 dB Implied Fiber Loss
=
19 dB
.25 dB
76 km Maximum Transmission Distance
=
÷
Summary of Contents for 10292FA
Page 10: ...10 Figures 212257 B ...
Page 12: ...12 Tables 212257 B ...
Page 16: ...16 Preface 212257 B ...
Page 26: ...26 Chapter 1 Describing the optical routing system 212257 B ...
Page 46: ...46 Appendix A CWDM OADM specifications 212257 B ...
Page 48: ...48 Appendix B CWDM OMUX specifications 212257 B ...
Page 54: ...54 Appendix C Handling and cleaning fiber optic equipment 212257 B ...
Page 66: ...66 Glossary 212257 B ...
Page 70: ...70 Index 212257 B ...