30
4.10.2
General Installation Instructions using
the 44658-78
Ensure sprayer power is turned off.
Figure 33 – Cable Routing Overview (Using 44658-78)
1.
Connect the UC4 power cable (
C10
) to the
UC4+ Control Panel in the cab. Ensure that
both plugs (
P16
and
P4
) are connected to
the panel.
2.
Route the 22-pin AMP receptacle (
R22
) of
C10 to the exterior of the cab.
3.
Connect the 22-pin AMP plug (
P22
) of the
extension cable (
C11
) to R22 of C10.
Position this connection near the hitch. This
will provide the hitch disconnect.
4.
Run cable C11 from the hitch to the rear of
the sprayer.
5.
Install the sensor branch cable (
C02
) along
the boom between the ultrasonic sensors.
Be sure to route the cable through the
boom to avoid damage to the cable during
field operation or boom folding. Connect
cable C02 to cable C02A. Connect cable
C02A to cable C11.
6.
Connect T4, T6 and S6 of cable C11 to S4,
S6 and T6 of cable C12 respectively.
7.
Run the DB15 connector and the wires with
the spade connectors of C12 to the DAH 09
PCB by passing it through a hole in the
enclosure. Seal the hole using the weather-
proof strain relief fitting.
8.
Connect the DB15 connector of cable C12
to the DAH09 DB15 connector.
9.
Connect the red wire with spade connector
on C12 to the Switched 12VCC on the
DAH09 board (
Figure 34
).
10.
Connect the black wire with spade
connector on C12 to the GND on the
DAH09 board (
Figure 34
).
Summary of Contents for UC4+ Roll Control
Page 11: ...7 Figure 4 Hydraulic Plumbing Schematic ...
Page 40: ...36 6 3 ITEM C3 44656D CABLE VALVE VARIABLE RATE DT ...
Page 41: ...37 6 4 ITEM C10 44658 52 CABLE UC4 BC POWER C10 HARDI ...
Page 42: ...38 6 5 ITEM C11 44658 50 CABLE UC4 BC EXTENSION C11 HARDI ...
Page 43: ...39 6 6 ITEM C12A 44658 51 CABLE UC4 BC INTERFACE HARDI DAH ...
Page 44: ...40 6 7 ITEM C12 44658 78 CABLE UC4 BC INTERFACE HARDI DAH 09 ...