18
4.6.2 Valve Mounting
1.
Mount the NORAC valve (
V01
) on the
sprayer using the valve mounting bracket
(
B10
).
2.
As shown in
Figure 21
, screw short side of
the threaded rods into the bottom of the valve
block at least 3/8". The valve mounting holes
are drilled and tapped 3/8 NC-1" deep.
3.
Tighten the Hex nuts to hold the rods.
4.
Put the mounting bracket on the other side of
the tube and tighten with the spring washers
and the Hex nuts. Cut excess off of the rods,
if necessary.
If using bolts, the bolts should thread
into the valve block at least 3/8". The
valve mounting holes are drilled and
tapped 3/8 NC-1" deep. The rule of
thumb for bolt length is 1-1/2" longer
than the tube size.
You must ensure no hydraulic
components will interfere with any
sprayer parts or be pulled tight at any
time.
The recommended location for the
NORAC valve block is on the rear of
the boom center section on the
horizontal cross member, near the
existing valve block.
Figure 21 – Valve Mounting Location
Figure 22 – Valve Mounting Example
NORAC Valve
Block
Existing Valve
Block
Summary of Contents for UC4+ 1200/1600
Page 9: ...6 Figure 3 Hydraulic Components ...
Page 14: ...11 Figure 9 Sensor Serial Number Installation Location 3 SENSOR SYSTEM 5 SENSOR SYSTEM ...
Page 28: ...25 5 3 ITEM C03 44656 VALVE CABLE VARIABLE RATE ...
Page 29: ...26 5 4 ITEM C10 44650 35 POWER CABLE GENERIC PULL TYPE ...
Page 30: ...27 5 5 ITEM C11 44651 03 EXTENSION CABLE VALVE GENERIC ...
Page 31: ...28 5 6 ITEM C12 44658 38 ALL INTERFACE CABLE ...
Page 32: ...29 5 7 ITEM C16 44658 39 BYPASS INTERFACE CABLE ...