5.1 Select a Location for the Inverter

To select a location for the inverter the following criteria should be considered:

Do not install the inverter in unventilated confined space. To avoid poor performance 

or damage inverter, air flow is needed.

Exposure to direct sunlight will increase the operational temperature of the inverter 

andmay cause output power limiting. Ginlong recommend inverter installed to avoid 

directsunlight or raining.

Shaded or sheltered positions are recommended for maximum performance and 

service life.

Figure 5.1 Recommended installation position

4.

 

Installation

4.2 Product storage

Please use the original box to repackage the inverter, and retain the desiccant.

Packing

 

boxes

 

should

 

be

 

sealed

 

with

 

adhesive

 

tape.

Storage

 

temperature

 

should

 

be

 

kept

 

at

 -

25

℃-

60

℃,

and the relative humidity should

 

be

 

kept

 

between

 

0

 

to

 

95

%.

And

 

kept

 

no

 

condensation.

Please

 

avoid

 

the

 

chemical

 

corrosive

 

substances

,

because

 

it

 

maybe

 

corrod

 

the

 

inverter

.

The

 

packing

 

box

 

should

 

not

 

be

 

inclined

 

or

 

upside

 

down.

After

 

long

-

term

 

storage

the

 

inverter needs to be fully examined and tested by professional 

person before using.

If the inverter is not for using at present, it should be stored under the specific environment:

Please store the inverter in a clean and dry place, and keep it without the erosion of dust and 

vapor.

5.

 

Installation

The maximum cumulative number of layers should not be more than 4 when stack of multiple 

inverters.

The regular inspection is needed during the storage. If found the rat bite etc.,should replace the packing 

material in time

.11.

.10.

Summary of Contents for Solis-20K

Page 1: ...es Co Ltd No 57 Jintong Road Binhai Industrial Park Xiangshan Ningbo Zhejiang 315712 P R China Tel 86 0 574 6578 1806 Fax 86 0 574 6578 1606 If you encounter any problem on the inverter please find ou...

Page 2: ...n 2 Safety Instruction 2 1 Safety Symbols 2 2 General Safety Instruction 4 1 2 Packaging List 4 1 1 Induction 5 Installation 5 1 Select a Location for the Inverter 5 2 Mounting the Inverter 5 3 Electr...

Page 3: ...7 4 3 Version NO 7 4 4 Communication Data 7 4 5 Daily Energy Information 7 5 Advanced Settings Technicians Only 7 5 1 Select Grid Standard 7 5 2 Grid ON OFF 8 Maintenance 9 Trouble Shooting 10 Specif...

Page 4: ...followed during installation and maintenance Please read these instructions carefully before use and keep them for future reference 2 2 General Safety Instructions WARNING Electrical installations mu...

Page 5: ...PD are required for circuits connected to the Inverter The recommended rated trip current of OCPD Solis 20K should be 40A Solis 25K Solis 30K Solis 30K HE Solis 36K HV and Solis 40K HV should be 63A C...

Page 6: ...nverter is operating properly The inverter has stopped supplying power The inverter is initializing Alarm or fault condition is detected The inverter is operating properly Status ON OFF ON OFF OFF ON...

Page 7: ...desiccant Packing boxes should be sealed with adhesive tape Storage temperature should be kept at 25 60 and the relative humidity should be kept between 0 to 95 And kept no condensation Please avoid t...

Page 8: ...llows Figure 5 3 The dimensions of the mounting bracket 3 Using the expansion bolts to fix the bracket to the wall Install on a vertical surface or structure capable of bearing the weight Must install...

Page 9: ...rical installations must be in accordance with all local and national standards Table 5 1 Electrical connection symbols GRID COM1 Connecting terminal of the Grid DC 1 input terminal DC 1 DC4 _ Positiv...

Page 10: ...onnectors to the Inverter Figure 5 7 DC Connector Figure 5 8 DC Connector B Connect the DC and DC to the input terminals see Figure 5 7 and Figure 5 8 A Please make sure the polarity of the output vol...

Page 11: ...20mm 20 9mm 2 80mm 100mm 10mm 12 9mm 13mm 15 9mm 16mm 16 9mm For all AC connections 10 35mm 105 cable is required to be used 2 Please make sure the resistance of cable is lower than 1 5 ohm If the wi...

Page 12: ...oring solution Please refer to related instructions of Ginlong communication products Figure 5 17 Connect cable to AC terminal Figure 5 18 Tighten the AC terminal Rs485 communication connection of RJ4...

Page 13: ...oring device or RS232 converter Pin 1 and 4 are defined as RS485 A while pin 2 and 5 are defined as RS485 B 6 2 Stop the inverter To stop the Solis three phase string inverter it is important to follo...

Page 14: ...total generation And through the bar chart we can view the generation information of the day Figure 7 2 The initial interface Power Now Today s Energy Monthly Energy 25 00kW 0054 4kWh 00491kWh Yearly...

Page 15: ...n Offset Ef ciency Generating 0003687kWh 0000014kWh 0000001kWh 0508kWh 2081kWh 0071 6kWh 000204kWh 50 01Hz 0003 67ton 99 99 E S C U P D O W N E N T 7 General Operation 7 General Operation 7 3 Settings...

Page 16: ...u Set Address 2015 02 23 19 35 Y E S E N T N O E S C Slave Address 01 E S C U P D O W N E N T Press the ESC key to cancel the change and return to the previous menu 7 General Operation 7 General Opera...

Page 17: ...ed manually by pressing the UP DOWN keys Pressing the ENTER key gives access to a submenu 7 4 1 Alarm Message The display shows the 10 latest alarm messages see Figure 7 14 Screens can be scrolled man...

Page 18: ...nverter see Figure 7 17 which is for service technicians only Figure 7 17 Communication data 7 4 5 Daily Energy Information The screen shows the daily energy detail of the inverter see Figure 7 18 Pre...

Page 19: ...fferent date Yearly Energy 2015 02 23 19 35 2015 0 0 0 5 1 0 1 5 2 0 2 5 3 0 Ye a r l y E n e r g y M W h 01 02 03 04 05 06 07 08 09 10 11 12 00 51 E S C U P D O W N E N T 7 General Operation 7 Genera...

Page 20: ...d settings Advanced Set 2015 02 23 19 35 Select Standard Grid ON OFF Power Control Clear Energy Restore Settings Calibrate Reset Password 7 General Operation 7 General Operation Press the UP DOWN keys...

Page 21: ...the previous menu NOTE The initial value of the User Def standard are for reference only It does not represents the correct value suitable for use Figure 7 26 Save cancel Save Cancel 2015 02 23 19 35...

Page 22: ...rking properly This function is applicable by maintenance personnel only wrong operation will prevent the inverter from reaching maximum power Press the DOWN key to move the cursor Press the UP key to...

Page 23: ...ting In case of a failure the LCD screen will display an alarm message In this case the inverter may stop feeding energy into the grid The alarm descriptions and their corresponding alarm messages are...

Page 24: ...operation range Max dc input current Number of MPPT strings per MPPT Rated output power Rated grid voltage The grid voltage range Operation phase Rated grid output current Output power factor The dc i...

Page 25: ...on Islanding protection VA C FA C in accordance with UL 1741 G59 3 AS4777 VDE 0126 1 1 VDE 4105 CEI 0 21 CQC 20years 46 47 1000V 380V 304 460Vac adjustable 0 99 50mA 50 60Hz 25 60 IP65 0 95 EN61000 6...

Page 26: ...DE 0126 1 1 VDE 4105 CEI 0 21 CQC 20years Operating Range Utility Frequency Model The max DC input voltage MPPT operation range Max dc input current Number of MPPT strings per MPPT Rated output power...

Reviews: