Cable routing
The following image shows recommended cable routing
from distribution box to condensation water trough in
F2016/F2026.. Transition between electrical cable and
heating cable must occur according to image.
1. Remove cover.
2. Thread hose clamp on.
3. Route the heating cable through the condensation
water pipe.
4. Remove the condensation water trough.
5. Route the heating cable through the drain pipe and
lead-in.
6. Pull the insulation down slightly, connect the hose
to the drain pipe and tighten the hose clamp.
7. Push the insulation up towards the trough and install
it using cable ties.
8. Lay the heating cable so that the marking is as close
to the drain pipe as possible.
9. Route the cable to the distribution box as illustrated.
(Extend the cable so that removal of the condensa-
tion water trough is possible, i.e. with some margin.)
10. Use factory fitted cable tie.
11. The distance between the distribution box and the
lead-in to the condensation water trough is approx.
2,000 mm.
12. The length of the non heat conducting section of
the cable needs adjusting. Roll the cable to the cor-
rect length (do not cut).
13. Connect the cable according to the "Electrical con-
nection" image. (Check fuse according to table. See
Fuse page 10.)
14. Reinstall the condensation water trough and cover.
NOTE
Ensure that the marking on the cable is edge to
edge with the drain (see image).
NOTE
Do not cut the heating cable!
L
EK
Drain spout
Marking
Lead in
Heating cable
9
Chapter 3 |
Electrical connection
Condensation water pipe KVR 10