5
2 System
Start
Up
2.1 Startup
Procedure
Provided that the power meter has been installed in an appropriate
environment and its power cord is connected to a working electrical outlet,
power-up the power meter by pressing the power button on the lower left
corner of the front panel.
For precise accuracy, 1936-R/2936-R Series power meters should be allowed
to warm up for one hour before being used for measurements.
2.2
Front Panel Keys
The front panel keys are organized in three groups (see Figure 2).
Navigation Keys
Reconfigurable (also called Soft) Keys
Escape (ESC) Key
Besides these keys, the front panel has a Power switch and a USB connector
on the left side of the instrument.
Figure 2
Front Panel keys
WARNING
To avoid electrical shock hazard, connect the instrument to
properly earth-grounded, 3-prong receptacles only. Failure to
observe this precaution can result in severe injury.
Navigation Keys
Dedicated Keys
Reconfigurable (Soft) Keys
USB Connector
Power Switch
Escape Key