INSTALLATIEHANDLEIDING – P13
VERSION 0129NM02INT01
INSTRUCTION MANUAL – P13 |
P13
06A0RNM20ENG05
Thank you for installing this charge point. Make sure
there is enough space to properly do the work.
Ensure to work safely and take the safety of others into
consideration as well, always work according to local
safety regulations. Ask the owner if there is anything
of significant importance that requires electricity in the
house, before you turn of the electricity.
When selecting the mounting location of the charge point,
ensure that future maintenance work can be carried out
safely without obstruction.
5.1 PREPARATION
Step 1: Prepare the cabling & RCD and MCB (conform to
local rules & regulations);
Step 2: Indicate which circuit(s) the charge point is
connected to in the distribution board;
Step 3: Turn the socket lid anti-clockwise and out of the
cover of the charge point;
Step 4: Then pull the cover from the rear edge to open
the charge point. Do not use any objects or tools to do
this.
5.2 MECHANICAL MOUNT
Step 1: Put the charge point back plate on the wall
to check its placement (charge point is leveled and
connector at +/- 1 m height). On the wall, mark the
positioning of the top two and bottom two attachment
points of the charge point and select the appropriate
fixtures (plugs, screws and washers);
Step 2: Drill all four holes and put the plugs in place;
Step 3: Place the two provided plastic spacers at the
backside of the bottom two attachment points. Secure
the charge point to the wall using the top two and
bottom two attachment points. Ensure that the rubber
and stainless steel washers are used and placed on the
back of the charge point at the bottom two attachment
points.
5.3 POWER CONNECTION
Step 1: Select the appropriate grommet that suits the
cable thickness and place it in the opening of the power
cable inlet. Lubcirate if necessary to make it easier to
feed the power cable through;
Step 2: Secure the power cable using the cable clamp;
Step 3: Connect the power to the terminal blocks, as
indicated in the ‘3.4.1 Overview of Connections | 7,4
kW Version’ or ‘3.4.2 Overview of Connections | 11 kW
Version’ section.
5.4A LOAD SHEDDING - CT FOR 7,4 KW
MODEL
The Current Transformer for Load Shedding (included
in box) must be connected to the phase used by the
charge point at the most upstream point of the house
grid, closest to the house grid connection.
Step 1: Install the CT on the same phase used by the
charge point, measuring the whole household. Place the
terminal block on a DIN-rail in the fusebox;
Step 2: Place a standard cable of 2x 1,5mm
2
(not
supplied) and connect two wires on both terminal blocks
in the charge point as indicated in the ’3.4.3 Overview
Installing Accessories’ section. Then place the cable
of 2x 1,5mm
2
to the CT ring on the side of the grid
connection. The maximum length of the cable is 100m.
5.4B LOAD SHEDDING MODULE FOR 11
KW MODEL
The Load Shedding Module package contains one Load
Shedding module, one power adapter and three current
transformers (CT’s). The CT’s must be connected at
the most upstream point of the house grid, closest to
the grid connection. Arrows are shown on the CT, but
direction is not important.
The connections for the CT’s are located at the bottom
of the Load Shedding module, and are labelled with
L1, L2 and L3 on the front label. L1, L2 and L3 must be
connected to the first, second and third phase of the
house grid in the correct order.
Although each measuring head is provided with two
different coloured threads, the polarity of connection is
not important.
The power cable connection on the terminal block of
the charge point should match the L1, L2 and L3 in the
charge point.
For a 1 phase installed charge point the L1 measurement
head should match the conduction which is connected
to the L1 of the terminal block.
Installation procedure
Step 1: Install the Load Shedding module on the DIN Rail
in the fuse box;
Step 2: Connect the CT(’s) to the Load Shedding
module, as described in the beginning of this paragraph;
Step 3: Apply the CT(’s) to the grid connection(s). Make
sure to apply the CT(’s) so that the total power usage of
the household is measured on each phase;
Step 4: Connect the power adapter to the Load
Shedding module. One of the two power adapter wires
5. INSTALLATION PROCEDURE